One of 2 filings for this project. The project's main page, with every filing and where each stands: Dabalikhurd Granite Quarry
Project details
| Status | Lapsed |
|---|---|
| Status since | 3 Feb 2025 |
| Application filed | 20 Dec 2023 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Mining |
| Applicant | Nepa Galaxy Mines |
| Land area | 4.9 acres (2 ha) |
| Project cost | ₹50 lakh |
| Village / locality | Dawali Kalan |
| Taluk / tehsil | Nepanagar |
| District | Burhanpur |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-00793 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Early planning filed 29 Jan 2025 | Cleared for impact study | 4.9 acres | ₹50 lakh |
| Ownership transfer filed 20 Dec 2023 (this page) | Lapsed | 4.9 acres | ₹50 lakh |
In context
56 applications in Burhanpur since January 2022 are in the same category (Mining): 35 approved, 4 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 4.9 acres, this one is smaller than 64% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Dawali Kalan, Nepanagar, Burhanpur, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Dabalikhurd Granite Quarry — cleared for impact study, 0 m away
- Ratagarh Stone Quarry — lapsed, 1.9 km away
- New 11 KV Line from Matapur to Chandani — lapsed, 4.2 km away
- Construction of Sewerage Plant — lapsed, 4.9 km away
- Municipal Council Proposes to Use 80.23 Hectares of Forest Land for… — lapsed, 5 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — lapsed, 5.9 km away
- Jio Digital Fiber Pvt Ltd OFC 5G Project in ROW Corridor of Principal road… — lapsed, 5.9 km away
- 33 KV Line from 220 KV Nepa Nagar — lapsed, 6.5 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.