One of 2 filings for this project. The project's main page, with every filing and where each stands: Rawad Stone Quarry
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 9 Sept 2023 |
| Application filed | 9 Sept 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Prathvi Infrastructure Private Limited |
| Land area | 9.4 acres (3.8 ha) |
| Project cost | ₹60 lakh |
| Village / locality | Rawad |
| Taluk / tehsil | Depalpur |
| District | Indore |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-01903 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 13 Mar 2024 | Environmental approval granted | 9.4 acres | ₹60 lakh |
| Early planning filed 9 Sept 2023 (this page) | Cleared for impact study | 9.4 acres | ₹60 lakh |
In context
129 applications in Indore since January 2022 are in the same category (Mining): 70 approved, 16 filed or under review, and 43 withdrawn, lapsed or rejected. The approved ones took a median of 13 days from filing to approval. At 9.4 acres, this one is larger than 67% of them.
3 other mining leases have applied within 500 m of this site; together with this one they cover 34.1 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 20 mining leases have applied within 5 km.
Where it is
Rawad, Depalpur, Indore, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Rawad Stone Quarry — environmental approval granted, 0 m away
- Common Municipal Solid Waste Management Facility (CMSWMF) at Betma & its… — lapsed, 400 m away
- Rawad Stone & M-sand Quarry — cleared for impact study, 400 m away
- Rawad Stone & M-sand Quarry — environmental approval granted, 400 m away
- Rawad Stone (Gitti) & M-Sand Quarry — environmental approval granted, 500 m away
- Rawad Stone (Gitti) & M-Sand Quarry — cleared for impact study, 500 m away
- Rawad Crusher Stone Quarry of Shri Badrilal Dabar — environmental approval granted, 500 m away
- Rawad Stone Crusher Quarry Project — cleared for impact study, 500 m away
More from Prathvi Infrastructure Private Limited in Indore
- Jamanya Jagir Murram & Stone — not approved
- Jamanya Jagir Murram & Stone — cleared for impact study
- Jamanya Jagir Stone Quarry — lapsed
- Alwasa Stone Quarry — more information requested
6 Prathvi Infrastructure projects in Indore
All 15 Prathvi Infrastructure projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.