Quick answers
What is Area development of the Scheme No. 64 & 65?
Area development of the Scheme No. 64 & 65 is a proposed township project in Bahdan, Jabalpur, Madhya Pradesh. The site covers 460.6 acres.
Who is building it?
The applicant is Jabalpur Development Authority.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Bahdan, Jabalpur, Madhya Pradesh.
How big is it?
It has a stated cost of ₹245 crore and a site of 460.6 acres.
When was it filed?
The application was filed on 26 Sept 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 2 Oct 2026 |
| Application filed | 26 Sept 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Buildings & townships |
| Applicant | Jabalpur Development Authority |
| Use | Township |
| Land area | 460.6 acres (186.4 ha) |
| Plot area | 18,64,000 m² (2,00,63,910 sq ft) |
| Project cost | ₹245 crore |
| Village / locality | Bahdan |
| Taluk / tehsil | Jabalpur |
| District | Jabalpur |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-08486 |
What the filings say
What is planned
The Jabalpur Development Authority (JDA) proposes an area development project covering Scheme No. 64 and Scheme No. 65. The project is strictly limited to land development and the provision of common civic infrastructure. After the land is developed, plots will be sold to prospective buyers who will independently undertake construction. The project report clarifies that while some plots are designated for industrial use, JDA will not establish or operate any industrial units itself.
The development is divided into two primary schemes:
- Scheme No. 64: This includes an industrial land-use area with plotted areas, a fire station, weighing machine area, substation, petrol pump, and police station. The residential land-use area within this scheme includes plotted areas, a shopping complex, marriage garden, hotel area, nursing home/health centre, community centre, and school area.
- Scheme No. 65: This comprises an approved college area, residential area, local shopping centre, and public and semi-public areas.
Common infrastructure across both schemes includes water supply systems, stormwater drainage, sewerage networks, a Sewage Treatment Plant (STP), gardens, green areas, parking facilities, and internal roads.
| Item | Detail |
|---|---|
| Total Project Area | 186.4 hectares (460.6 acres) |
| Total Project Cost | ₹245 crore |
| Total Power Requirement | 36.488 MW |
| Operational Water Demand | 14,150 KLD |
| Wastewater Generation | 11,894 KLD |
| Proposed STP Capacity | 10,740 KLD |
| Total Tree Plantation | 23,408 saplings |
Layout and design
The site layout incorporates a hierarchy of roads, including 48m, 18m, 15m, 12m, and 9m wide internal roads. The design includes a 30m wide green belt. JDA's scope is limited to infrastructure; therefore, building-specific parameters like Built-up Area, Floor Space Index (FSI), and dwelling unit counts are marked as not applicable at this stage, as they will be the responsibility of individual plot owners.
Land and surroundings
The project is spread across 186.4 hectares in the villages of Mohania, Bahdan, Simariya, Basha, Gadha, and Kachnari in Jabalpur District. The land is government-owned and recorded as already acquired. The site soil is classified as light reddish-brown clayey silty soil.
Sensitive receptors within the vicinity include Supatal Lake (3.4 km), Vijay Nagar (2 km), and Medizone Multi-Speciality Hospital (2 km). No forest land or protected areas are located within a 10 km radius.
Water, power and access
Water: During the operational phase, 14,150 KLD of water will be sourced from the Jabalpur Municipal Corporation. This includes 8,938 KLD for drinking, 4,402 KLD for flushing, and 810 KLD for the green belt. Construction water (6.3 KLD) will be supplied via tankers.
Power: Electricity (36.488 MW) will be sourced from Madhya Pradesh Poorv Kshetra Vidyut Vitran Company Limited (MPPKVVCL). Individual plot owners are expected to install rooftop solar panels, as no centralised renewable energy system is proposed by JDA.
Access: The site is connected via the Jabalpur Bypass Road (1.31 km). The nearest railway station is Kachhpura (2.78 km), and Jabalpur Airport is approximately 18.4 km away.
Environmental safeguards
Wastewater: The project will employ a Zero Liquid Discharge (ZLD) system. Two STP units using Sequencing Batch Reactor (SBR) technology, each with a capacity of 5,370 KLD, are proposed. Treated water will be reused for flushing and landscaping, with surplus supplied to nearby industries for non-potable use.
Solid Waste: Operational waste is estimated at 18,334 tonnes per annum (TPA), consisting of 8,659 TPA biodegradable and 9,675 TPA non-biodegradable waste. This will be collected and handed over to the Jabalpur Municipal Corporation.
Green Belt and Drainage: A green belt covering 18.64 hectares (10% of the plot area) is planned. While 110 existing trees will be cut for road alignment, JDA proposes a compensatory plantation at a 1:3 ratio and a total plantation of 23,408 saplings. For stormwater, 163 recharge pits are proposed along roads and green areas to facilitate groundwater recharge.
Construction Management: The project involves balanced cut-and-fill operations of 1,60,971 cubic metres, meaning all excavated earth will be reused on-site for levelling and landscaping.
Area Development of the Scheme No. 64 & 65 site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
15 applications in Jabalpur since January 2022 are in the same category (Buildings & townships): 8 approved, 6 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 31 days from filing to approval. At 460.6 acres, this one is larger than 73% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bahdan, Jabalpur, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed area development of Scheme No-64 & No-65 project by Jabalpur… — under environmental review, 0 m away
- Proposed area development of Scheme No-64 & No-65 project by Jabalpur… — cleared for impact study, 0 m away
- Diversion of 9.2408 ha. Forest Land for Jabalpur Ring Road Section 2 — forest land use approved, 2.7 km away
- Datt Solitare Developer Datt Real Infra PVT. LTD. Phase - 1 & 3 — under environmental review, 4.7 km away
- Proposed project for the area development of Residential Scheme TDS 2 by… — cleared for impact study, 5 km away
- Diversion of 9.466 ha. Forest Land for Jabalpur Ring Road Section 4. — forest land use approved, 5.2 km away
- Samdariya Avenue Residential/Commercial Complex Jabalpur — environmental approval granted, 6.1 km away
- Samdariya Avenue Residential/Commercial Complex Jabalpur — withdrawn, 6.1 km away
More from Jabalpur Development Authority in Jabalpur
- Proposed area development of Scheme No-64 & No-65 project by Jabalpur… — under environmental review
- Proposed project for the area development of Residential Scheme TDS 2 by… — cleared for impact study
- Proposed area development of Scheme No-64 & No-65 project by Jabalpur… — cleared for impact study
All 4 Jabalpur Development Authority projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.