| Official title | Jhabua Power Limited- 33 KV Insulated Transmission Line Above the Ground at Village -Bagdari |
|---|---|
| Status | Forest land use approved |
| Status since | 21 Feb 2025 |
| Application filed | 20 May 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Jhabua Power Limited |
| Land area | 2,400 m² |
| Forest land | 2,400 m² |
| Project cost | ₹50 lakh |
| Village / locality | Bagdari |
| Taluk / tehsil | Ghansaur |
| District | Seoni |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-09218 |
In context
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bagdari, Ghansaur, Seoni, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- JHABUA POWER LIMITED -A 33 KV Transmission line at Village- Bagdari — forest land use approved, 1.8 km away
- Diversion of 32.5059 Ha of Forest Land for Construction of Ash Dyke — under forest review, 7.8 km away
- Diversion of 1.85 Ha of Forest Land for Installation of Cooling Tower — more information requested, 7.9 km away
- Surrender of Environmental Clearance (EC) granted for Expansion of Power… — lapsed, 8.1 km away
- Expansion of Existing Capacity of Thermal Power Plant From 600 MW to 1400 MW… — returned to applicant, 8.4 km away
- Environmental Clearance for Expansion in existing capacity of power plant from… — returned to applicant, 8.4 km away
- Jio Digital Fiber Pvt Ltd OFC 5G Project in RoW Corridor of Principal Road… — forest land use approved, 9.5 km away
- Binekikala Crusher Stone, M-Sand & Boulder Quarry Lease — under environmental review, 12.4 km away
More from Jhabua Power Limited in Seoni
- Diversion of 32.5059 Ha of Forest Land for Construction of Ash Dyke — under forest review
- Diversion of 1.85 Ha of Forest Land for Installation of Cooling Tower — more information requested
- Expansion of Existing Capacity of Thermal Power Plant From 600 MW to 1400 MW… — returned to applicant
- Environmental Clearance for Expansion in existing capacity of power plant from… — returned to applicant
- Surrender of Environmental Clearance (EC) granted for Expansion of Power… — lapsed
- JHABUA POWER LIMITED -A 33 KV Transmission line at Village- Bagdari — forest land use approved
All 7 Jhabua Power projects across India