Quick answers
What is Gondbahera Ujheni Underground Coal mine?
Gondbahera Ujheni Underground Coal mine is an approved mining project in Tinguri, Deosar, Singrauli, Madhya Pradesh. The site covers 4,759.9 acres.
Who is building it?
The applicant is Mp Natural Resources Private Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 12 Aug 2025), as of 27 Nov 2026.
Where is it?
In Tinguri, Deosar, Singrauli, Madhya Pradesh.
How big is it?
It has a stated cost of ₹2,464 crore; a site of 4,759.9 acres and 1,141.1 acres (461.8 ha) of forest land.
When was it filed?
The application was filed on 31 May 2024.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 12 Aug 2025 |
| Application filed | 31 May 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Mining |
| Applicant | Mp Natural Resources Private Limited |
| Land area | 4,759.9 acres (1,926.3 ha) |
| Forest land | 1,141.1 acres (461.8 ha) |
| Project cost | ₹2,464 crore |
| Village / locality | Tinguri |
| Taluk / tehsil | Deosar |
| District | Singrauli |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-09246 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Early planning filed 14 Jun 2024 | Cleared for impact study | 4,759.9 acres | ₹2,464 crore |
| New project filed 31 May 2024 (this page) | Forest land use approved | 4,759.9 acres | ₹2,464 crore |
In context
268 applications in Singrauli since January 2022 are in the same category (Mining): 152 approved, 40 filed or under review, and 76 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 4,759.9 acres, this one is larger than 91% of them.
2 other mining leases have applied within 500 m of this site; together with this one they cover 14,841.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 4 mining leases have applied within 5 km.
Where it is
Tinguri, Deosar, Singrauli, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Gondbahera Ujheni Underground Coal mine — environmental approval granted, 0 m away
- Gondbahera Ujheni Underground Coal mine — cleared for impact study, 0 m away
- "Gondbahera Ujheni Underground Coal Mine" (2040 ha) rated capacity of coal is… — returned to applicant, 100 m away
- "Gondbahera Ujheni Underground Coal Mine" (2040 ha) with rated capacity of… — withdrawn, 100 m away
- Talwa Sand Deposit — more information requested, 2.6 km away
- Pachaur Coal Block — initial checks, 3.3 km away
- Gondbahera Ujheni East Coal Mine — environmental approval granted, 4.3 km away
- Gondbahera Ujheni East Coal Mine — forest land use approved, 4.3 km away
More from Mp Natural Resources Private Limited in Singrauli
- Gondbahera Ujheni Underground Coal mine — environmental approval granted
- "Gondbahera Ujheni Underground Coal Mine" (2040 ha) rated capacity of coal is… — returned to applicant
- "Gondbahera Ujheni Underground Coal Mine" (2040 ha) with rated capacity of… — withdrawn
- Gondbahera Ujheni East Coal Mine — forest land use approved
All 6 Mp Natural Resources projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.