Quick answers
What is 33KV New Electric Line (Under RDSS Scheme)?
33KV New Electric Line (Under RDSS Scheme) is a lapsed power project in Bagwaj, Sheopur, Madhya Pradesh. The site covers 7.9 acres.
Who is building it?
The applicant is Rural Development.
Has it been approved?
No. The application was lapsed on 3 Nov 2025, so it is no longer under consideration.
Where is it?
In Bagwaj, Sheopur, Madhya Pradesh.
How big is it?
It has a stated cost of ₹22 lakh; a site of 7.9 acres and 7.9 acres (3.2 ha) of forest land.
When was it filed?
The application was filed on 22 Dec 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 3 Nov 2025 |
| Application filed | 22 Dec 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Rural Development |
| Land area | 7.9 acres (3.2 ha) |
| Forest land | 7.9 acres (3.2 ha) |
| Project cost | ₹22 lakh |
| Village / locality | Bagwaj |
| Taluk / tehsil | Sheopur |
| District | Sheopur |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-09357 |
In context
11 applications in Sheopur since January 2022 are in the same category (Power): 1 approved, 7 filed or under review, and 3 withdrawn, lapsed or rejected. At 7.9 acres, this one is smaller than 80% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bagwaj, Sheopur, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 33 KV Mau Feeder (RDSS) — forest land use approved, 50 m away
- Kasba Sheopur Crusher Stone mine for making Boulder, Gitti & M-sand — environmental approval granted, 3 km away
- Kasba Sheopur Stone (Boulder) Quarry — environmental approval granted, 3.3 km away
- Kasba Sheopur Stone (Gitti, M-Sand, Boulder & Murrum) Mine of Ravindra… — cleared for impact study, 3.3 km away
- Kasba Stone Quarry — environmental approval granted, 3.4 km away
- Kasba Sheopur Stone (Boulder & M-Sand) Mine of M/S Shreeji Enterprises — under environmental review, 3.6 km away
- Mukundpura Soil Quarry — environmental approval granted, 5.8 km away
- Bardha Bujarg Soil Quarry — environmental approval granted, 6.1 km away
More from Rural Development in Sheopur
- New 33 KV Line For Bhojka Substation — more information requested
- New 33 KV Line ADRDE — more information requested
- 33 KV Agra to Magardeh — more information requested
- New 33 Kv Line Shyampur — under forest review
- Chakrampura New 11KV feeder under Feeder separation Project — more information requested
- 11 KV Line Ochha to Ghamloki under RDSS — more information requested
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.