What is Imaliya to Dabar Kho Road?
Imaliya to Dabar Kho Road is a lapsed road project in Imalia, Shivpuri, Madhya Pradesh. It seeks 6.5 acres of forest land.
Who is building it?
The applicant is Public Works Department.
Has it been approved?
No. The application was lapsed on 6 Feb 2025, so it is no longer under consideration.
Where is it?
In Imalia, Shivpuri, Madhya Pradesh.
How big is it?
It has a stated cost of ₹3.9 crore and 6.5 acres (2.6 ha) of forest land.
When was it filed?
The application was filed on 2 Jan 2025.
One of 3 filings for this project. The project's main page, with every filing and where each stands: Imaliya to Dabar Kho Road
Project details
| Status | Lapsed |
|---|---|
| Status since | 6 Feb 2025 |
| Application filed | 2 Jan 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Public Works Department |
| Forest land | 6.5 acres (2.6 ha) |
| Project cost | ₹3.9 crore |
| Village / locality | Imalia |
| Taluk / tehsil | Shivpuri |
| District | Shivpuri |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-09808 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 23 May 2025 | Lapsed | ₹3.9 crore | |
| New project filed 7 Mar 2025 | Lapsed | ₹3.9 crore | |
| New project filed 2 Jan 2025 (this page) | Lapsed | ₹3.9 crore |
In context
32 applications in Shivpuri since January 2022 are in the same category (Roads & highways): 5 approved, 10 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Imalia, Shivpuri, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Imaliya to Dabar Kho Road — lapsed, 0 m away
- Imaliya to Dabar Kho Road — lapsed, 0 m away
- Kherona Flag Stone Mine — environmental approval granted, 4.5 km away
- Kherona Flag Stone Mine — cleared for impact study, 4.5 km away
- OFC Laying Work from Mohna -shashram-Tetra route in RoW DFO Gwalior — initial checks, 5.7 km away
- 11KV Govardhan DLF Feeder Bifurcation Line Under Rdss Scheme — lapsed, 8.6 km away
- Jio Digital Fiber Pvt. Ltd. Linear OFC 5G Project In Row Corridor of Principal… — forest land use approved, 10.4 km away
- Bharti Airtel Ltd. 5G OFC Project BAMHARI DFO Shivpuri — forest land use approved, 11.1 km away
More from Public Works Department in Shivpuri
- Nayagaon to Chhirari Road Length 14.00 Km Distt. Shivpuri (M.P.) With Over… — lapsed
- Nayagaon to Chhirari Road Length 14.00 Km Distt. Shivpuri (M.P.) With Over… — lapsed
- Upgradation & Construction Of Shivpuri Jhansi Link Road — more information requested
- Upgradation & Construction of Shivpuri Jhansi Link Road — more information requested
7 Public Works Department, Madhya Pradesh projects in Shivpuri
All 40 Public Works Department, Madhya Pradesh projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.