Project details
| Status | Lapsed |
|---|---|
| Status since | 7 Mar 2025 |
| Application filed | 31 Jan 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Adani Energy Solutions Step-Eleven Limited |
| Land area | 3,704.1 acres (1,499 ha) |
| Forest land | 471.8 acres (190.9 ha) |
| Project cost | ₹297.3 crore |
| Village / locality | Mohaniyan |
| Taluk / tehsil | Churhat |
| District | Sidhi |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-09930 |
In context
8 applications in Sidhi since January 2022 are in the same category (Power): 2 approved, 3 filed or under review, and 2 withdrawn, lapsed or rejected.
Where it is
Mohaniyan, Churhat, Sidhi, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 400 KV D/C Rewa-Mahan Transmission Line — more information requested, 7.9 km away
- 400 KV D/C Mahan-Reewa Transmission Line — under wildlife review, 10.1 km away
- Dalapiper Sand Deposit — environmental approval granted, 10.7 km away
- Construction of Sidhi-Sirsi Road — forest land use approved, 11 km away
- Bharti Airtel Limited 5G OFC Project Sidhi_Singrauli_Pondi_Singrauli route DFO… — forest land use approved, 11.2 km away
- Padri Sand Quarry — under environmental review, 11.3 km away
- Padri Sand Deposit — environmental approval granted, 11.7 km away
- Tikri -1 Sand Deposit_2.00 ha — cleared for impact study, 12.8 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.