Quick answers
What is this project?
33 KV Line for 33/11 KV Substation Shergarh under RDSS Scheme is a lapsed power project in Shergarh, Pichhore, Shivpuri, Madhya Pradesh. The site covers 8.9 acres.
Who is building it?
The applicant is MADHYA PRADESH MADHYA KSHETRA VIDUT VITaran com.
Has it been approved?
No. The application was lapsed on 19 Dec 2024, so it is no longer under consideration.
Where is it?
In Shergarh, Pichhore, Shivpuri, Madhya Pradesh.
How big is it?
It has a stated cost of ₹10 lakh; a site of 8.9 acres and 2.4 acres (1 ha) of forest land.
When was it filed?
The application was filed on 4 Oct 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 19 Dec 2024 |
| Application filed | 4 Oct 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | MADHYA PRADESH MADHYA KSHETRA VIDUT VITaran com |
| Land area | 8.9 acres (3.6 ha) |
| Forest land | 2.4 acres (1 ha) |
| Project cost | ₹10 lakh |
| Village / locality | Shergarh |
| Taluk / tehsil | Pichhore |
| District | Shivpuri |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-10098 |
In context
10 applications in Shivpuri since January 2022 are in the same category (Power): 2 approved, 1 filed or under review, and 7 withdrawn, lapsed or rejected.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Shergarh, Pichhore, Shivpuri, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 33KV Line Interconnection Under Rdss Loss Reduction Scheme — forest land use approved, 1000 m away
- Khadela Flagstone Quarry — environmental approval granted, 3.2 km away
- Khadela Flagstone Quarry — lapsed, 3.2 km away
- Sangatha (Aer) Medium Project — environmental approval granted, 6.6 km away
- Todi Karera & Aaspur Stone (Gitti) & M-Sand Quarry — environmental approval granted, 9.3 km away
- Bhadora Flagstone, Khanda/ Dhoka Quarry — under environmental review, 9.5 km away
- Bhadora Flagstone Quarry — environmental approval granted, 10 km away
- Bhadora Flagstone Quarry — environmental approval granted, 10.5 km away
More from MADHYA PRADESH MADHYA KSHETRA VIDUT VITaran com in Shivpuri
- 11KV Govardhan DLF Feeder Bifurcation Line Under Rdss Loss Reduction Scheme — lapsed
- 11KV Govardhan DLF Feeder Bifurcation Line Under Rdss Scheme — lapsed
- 11kV Charch Feeder under RDSS PROJECT — lapsed
- 11KV Bhatnawar DLF feeder extension under PVTG scheme — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.