Quick answers
What is Khalwa Lift Micro Irrigation Scheme Phase-Ii?
Khalwa Lift Micro Irrigation Scheme Phase-Ii is an approved water and irrigation project in Udiyapur, Khalwa, East Nimar, Madhya Pradesh. The site covers 6.8 acres.
Who is building it?
The applicant is Ee Nd Division No Nineteen Bhikangaon.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 14 Apr 2026), as of 27 Nov 2026.
Where is it?
In Udiyapur, Khalwa, East Nimar, Madhya Pradesh.
How big is it?
It has a stated cost of ₹201.6 crore; a site of 6.8 acres and 1.8 acres (0.7 ha) of forest land.
When was it filed?
The application was filed on 8 Jan 2024.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 14 Apr 2026 |
| Application filed | 8 Jan 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Ee Nd Division No Nineteen Bhikangaon |
| Land area | 6.8 acres (2.7 ha) |
| Forest land | 1.8 acres (0.7 ha) |
| Project cost | ₹201.6 crore |
| Village / locality | Udiyapur |
| Taluk / tehsil | Khalwa |
| District | East Nimar |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-10252 |
In context
17 applications in East Nimar since January 2022 are in the same category (Water & irrigation): 11 approved, 1 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 9 months from filing to approval. At 6.8 acres, this one is smaller than 75% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Udiyapur, Khalwa, East Nimar, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Bharti Airtel Limited Project Harda-Roshni-Khalwa-Tukaithad route, district… — forest land use approved, 3.8 km away
- Mendhapani Stone Quarry (Temporary Permit) — lapsed, 4.4 km away
- IPCA 30 MV Solar Plant — forest land use approved, 5 km away
- HARDA - ASHAPUR Road — lapsed, 5.1 km away
- Construction of 132KV Chhanera-Singot DCSS Transmission Line — more information requested, 5.4 km away
- 33KV Roshani Feeder Bifurcation — more information requested, 5.8 km away
- Diversion of 0.0411 Ha of Forest Land for Construction of Mobile Tower — lapsed, 5.8 km away
- Approach Road for PH: Khalwa MLIS — in-principle approval, conditions pending, 5.9 km away
More from Ee Nd Division No Nineteen Bhikangaon in East Nimar
- Approach Road for PH: Khalwa MLIS — in-principle approval, conditions pending
- Khalwa Lift Micro Irrigation Scheme Phase-Ii — environmental approval granted