What is Maa Rewa Lift Irrigation Project?
Maa Rewa Lift Irrigation Project is a lapsed water and irrigation project in Ajnas, Khategaon, Dewas, Madhya Pradesh. The site covers 25.4 acres.
Who is building it?
The applicant is Madhya Pradesh Water Resources Department.
Has it been approved?
No. The application was lapsed on 1 Apr 2026, so it is no longer under consideration.
Where is it?
In Ajnas, Khategaon, Dewas, Madhya Pradesh.
How big is it?
It has a stated cost of ₹862.5 crore; a site of 25.4 acres and 7.1 acres (2.9 ha) of forest land.
When was it filed?
The application was filed on 18 Mar 2025.
Project details
| Status | Lapsed |
|---|---|
| Status since | 1 Apr 2026 |
| Application filed | 18 Mar 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Madhya Pradesh Water Resources Department |
| Land area | 25.4 acres (10.3 ha) |
| Forest land | 7.1 acres (2.9 ha) |
| Project cost | ₹862.5 crore |
| Village / locality | Ajnas |
| Taluk / tehsil | Khategaon |
| District | Dewas |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-10735 |
In context
18 applications in Dewas since January 2022 are in the same category (Water & irrigation): 10 approved, 5 filed or under review, and 2 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 25.4 acres, this one is smaller than 53% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ajnas, Khategaon, Dewas, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 220 KV DCDS Ashta Kannod Transmission Line — lapsed, 1.1 km away
- Sukras Quartzite Mine — lapsed, 5.4 km away
- Sukras Quartzite Mine — cleared for impact study, 5.4 km away
- NANASA QUARTZITE & QUARTZITIC SAND, KHANDA, DHOKHA, DRESSED STONE (BLOCK) Mine — lapsed, 5.4 km away
- Sukras Crusher Stone (Gitti & Sand Material), Dhokha, Khanda, Polished Stone… — lapsed, 5.4 km away
- Nanasa Quartzite and Quartzitic Sand Quarry — more information requested, 5.4 km away
- Nanasa Quartzite & Quartzitic Sand, Khanda, Dhokha Dressed Stone (Block)quarry — cleared for impact study, 5.5 km away
- Sukras Quartzite Deposit — more information requested, 5.5 km away
More from Madhya Pradesh Water Resources Department in Dewas
- Maa Rewa Lift Irrigation Project in Dewas, Madhya Pradesh — under forest review
- Patpadi Tank Project Pipeline — more information requested
- Maa Rewa Lift Irrigation Project in Dewas, Madhya Pradesh — cleared for impact study
- Hatpipaliya Micro Lift Irrigation Project — more information requested
- Hat Pipaliya Micro Lift Irrigation Project — environmental approval granted
- Richikho Barrage Project — under wildlife review
8 Madhya Pradesh Water Resources Department projects in Dewas
All 20 Madhya Pradesh Water Resources Department projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.