Quick answers
What is 400 kV D/c Neemuch-Chittorgarh?
400 kV D/c Neemuch-Chittorgarh is an approved power project in Dharari, Singoli, Neemuch, Madhya Pradesh. It seeks 48.1 acres of forest land.
Who is building it?
The applicant is Powergrid Neemuch Transmission System Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 4 May 2026), as of 27 Nov 2026.
Where is it?
In Dharari, Singoli, Neemuch, Madhya Pradesh.
How big is it?
It has a stated cost of ₹324.5 crore and 48.1 acres (19.5 ha) of forest land.
When was it filed?
The application was filed on 23 Mar 2023.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 4 May 2026 |
| Application filed | 23 Mar 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Powergrid Neemuch Transmission System Limited |
| Forest land | 48.1 acres (19.5 ha) |
| Project cost | ₹324.5 crore |
| Village / locality | Dharari |
| Taluk / tehsil | Singoli |
| District | Neemuch |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-11097 |
In context
15 applications in Neemuch since January 2022 are in the same category (Power): 7 approved, 2 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 14 months from filing to approval.
Where it is
Dharari, Singoli, Neemuch, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 220kV D/C Neemuch SS(PG) to Chanderiya (132/220kV Switching SS) Transmission… — forest land use approved, 11.6 km away
- Construction of Pipliyajagir to Harwar Road Via Jaleshwar Mahadev — lapsed, 11.8 km away
- Gandhi Sagar 2 Multi-Villages Scheme — forest land use approved, 13.7 km away
- Construction of Ratangarh-Jat-Laxmipur-Vijaypur Road — more information requested, 14.1 km away
- Arniya to Mendhkeshwar Mahadev Mandir Road — more information requested, 17 km away
- Neemuch - Singoli (upto MP/RJ State Border) Road — under forest review, 18.6 km away
- Kholpura Stone Quarry — environmental approval granted, 19 km away
- ACME 220KV D/C Overhead Transmission Line for 300 MW Solar Project — forest land use approved, 21.1 km away
All 5 Powergrid Neemuch Transmission projects across India