What is Construction of Itariya to Pashchim Nimar Kakoda Road?
Construction of Itariya to Pashchim Nimar Kakoda Road is a lapsed road project in Kakora, Pandhana, East Nimar, Madhya Pradesh. The site covers 7.5 acres.
Who is building it?
The applicant is Pwd Division Burhanpur.
Has it been approved?
No. The application was lapsed on 1 Sept 2026, so it is no longer under consideration.
Where is it?
In Kakora, Pandhana, East Nimar, Madhya Pradesh.
How big is it?
It has a stated cost of ₹10 crore; a site of 7.5 acres and 2.4 acres (1 ha) of forest land.
When was it filed?
The application was filed on 4 Sept 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 1 Sept 2026 |
| Application filed | 4 Sept 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Pwd Division Burhanpur |
| Land area | 7.5 acres (3.1 ha) |
| Forest land | 2.4 acres (1 ha) |
| Project cost | ₹10 crore |
| Village / locality | Kakora |
| Taluk / tehsil | Pandhana |
| District | East Nimar |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-11639 |
In context
33 applications in East Nimar since January 2022 are in the same category (Roads & highways): 6 approved, 14 filed or under review, and 13 withdrawn, lapsed or rejected. The approved ones took a median of 10 months from filing to approval. At 7.5 acres, this one is larger than 59% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kakora, Pandhana, East Nimar, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Itariya Stone Quarry — not approved, 3.9 km away
- Widening of Sukta (Shivababa) to Itariya Road — forest land use approved, 6.1 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — lapsed, 6.4 km away
- New 33/11 KV SubStation Badoda Ahir — forest land use approved, 7.4 km away
- Goradiya Stone Mine-2.150ha — environmental approval granted, 10.7 km away
- Goradiya Stone Mine — lapsed, 10.7 km away
- Jhirniya Micro Lift Irrigation Project — environmental approval granted, 11.4 km away
- संयुक्त अनुविभागीय अधिकारी कार्यालय भवन निर्माण by Kumarshanu Deoriya — lapsed, 13 km away
More from Pwd Division Burhanpur in East Nimar
- Widening of Sukta (Shivababa) to Itariya Road — forest land use approved
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.