What is this project?
Nimapalli Stone Quarries Cluster (1,2,3,4,5 & 6) project, of Tahasildar Purushottampur is situated Near Village Nimapalli , Tahasil- Purushottampur District Ganjam, Odisha over an area of 72.971 acres or 29.528 hectares is a proposed mining project in Nimapalli, Purusottampur, Ganjam, Odisha. The site covers 73 acres.
Who is building it?
The applicant is Tahasildar Purushottampur.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 2 May 2023), as of 27 Nov 2026.
Where is it?
In Nimapalli, Purusottampur, Ganjam, Odisha.
How big is it?
It has a stated cost of ₹2 crore and a site of 73 acres.
When was it filed?
The application was filed on 2 May 2023.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 2 May 2023 |
| Application filed | 2 May 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Tahasildar Purushottampur |
| Land area | 73 acres (29.5 ha) |
| Project cost | ₹2 crore |
| Village / locality | Nimapalli |
| Taluk / tehsil | Purusottampur |
| District | Ganjam |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-00065 |
In context
235 applications in Ganjam since January 2022 are in the same category (Mining): 134 approved, 18 filed or under review, and 83 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 73 acres, this one is larger than 98% of them.
No other mining lease on record is within 500 m of this site; 6 have applied within 5 km.
Where it is
Nimapalli, Purusottampur, Ganjam, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Extension of validity of EC for production of 1.0 KLD Mahua Flower Based… — not approved, 3.5 km away
- Extension of validity of EC for production of 1.0 KLD Mahua Flower Based… — environmental approval granted, 3.5 km away
- Extension of validity of EC for production of 1.0 KLD Mahua Flower Based… — environmental approval granted, 3.5 km away
- Application for Environmental Clearance of Proposed Construction Road, Metal… — under environmental review, 3.9 km away
- Application for validity extension of Bhatakumarada Stone Quarry over an area… — lapsed, 3.9 km away
- Application for Environmental Clearance of Proposed Construction Road, Metal… — environmental approval granted, 3.9 km away
- Sunathar - C Stone Quarry Over an Area of 13.00 Acres Or 5.261 Hectares… — lapsed, 4.1 km away
- Sunathar - C Stone Quarry Over an Area of 13.00 Acres Or 5.261 Hectares… — environmental approval granted, 4.1 km away