Expansion of Grain Based Ethanol Plant from 360 KLD to 540KLD with Coal based Power Plant of 9 MW by M/s Mash Bio-Fuels Private Limited

Expansion of Grain Based Ethanol Plant from 360 KLD to 540KLD with Coal based Power Plant of 9 MW by M/s Mash Bio-Fuels Private Limited is a proposed industrial project in Kendumunda, Tarbha, Sonepur, Odisha. The site covers 56.7 acres. Its stated project cost is ₹256.6 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 9 Dec 2024).

See it on the live map All projects in Sonepur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusCleared for impact study
Status since9 Dec 2024
Application filed31 Aug 2024
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantM/S Mash Bio-Fuels PVT. LTD.
Land area56.7 acres (23 ha)
Project cost₹256.6 crore
Village / localityKendumunda
Taluk / tehsilTarbha
DistrictSonepur
StateOdisha
Location fromSite boundary on record
Our referenceWID-OR-00707

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 22 Dec 2025Lapsed56.7 acres₹256.6 crore
Early planning filed 31 Aug 2024 (this page)Cleared for impact study56.7 acres₹256.6 crore

In context

5 applications in Sonepur since January 2022 are in the same category (Industry): 3 approved, 0 filed or under review, and 2 withdrawn, lapsed or rejected.

3 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Kendumunda, Tarbha, Sonepur, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.