Quick answers
What is this project?
Residential Apartment Project "9 Emporio" by M/s NAWAH Corporate Private Limited is an approved residential project in Raghunathpur, Nandankanan, Khordha, Odisha. The site covers 1 acre.
Who is building it?
The applicant is Nawah Corporate Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 11 Jul 2024), as of 27 Nov 2026.
Where is it?
In Raghunathpur, Nandankanan, Khordha, Odisha.
How big is it?
It has a stated cost of ₹58 crore and a site of 1 acre.
When was it filed?
The application was filed on 5 Feb 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 11 Jul 2024 |
| Application filed | 5 Feb 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Nawah Corporate Private Limited |
| Use | Residential |
| Land area | 3,900 m² |
| Project cost | ₹58 crore |
| Village / locality | Raghunathpur |
| Taluk / tehsil | Nandankanan |
| District | Khordha |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-01005 |
What the filings say
What is planned
M/s Nawah Corporate Private Limited proposes to develop a residential apartment project named "9 Emporio" in Raghunathpur, Odisha. The project report describes a single building with a configuration of two basements, a stilt floor, and 34 upper floors (2B+S+34). The structure is planned to reach a maximum height of 111.15 metres up to the terrace level.
The development will comprise 96 residential dwelling units. The unit distribution includes:
- 4 BHK units: 91 nos.
- 6 BHK units: 3 nos.
- 3 BHK units: 2 nos.
The project also includes a society area of 145.86 square metres. The total population for the project is estimated at 771 persons, including 670 residents, 34 maintenance staff, and 68 visitors.
Project Area and Built-up Space
| Item | Detail |
|---|---|
| Total Plot Area | 3,925.32 m2 (0.97 acre) |
| Area affected by Road | 449.02 m2 |
| Net Plot Area | 3,476.30 m2 |
| Proposed Ground Coverage | 1,194.60 m2 (34.36% of net plot) |
| Total Proposed FAR | 20,846.43 m2 |
| Non-FAR (Parking and Services) | 8,053.36 m2 |
| Total Built-up Area | 28,899.79 m2 |
| Green Area | 697.25 m2 (20.06% of net plot) |
Layout and design
The site layout includes a 7.5-metre wide internal driveway surrounding the main building. Parking is distributed across basement, stilt, and open areas. The applicant proposes a total of 193 Equivalent Car Space (ECS) units, consisting of 172 covered spaces and 21 open spaces. Specific provisions are made for ambulance parking, physically challenged parking, and electric vehicle (EV) charging stations, which will cover at least 30% of the required parking area.
Land and surroundings
The project site is located at Raghunathpur Jali in the Nandankanan sub-district (Tehsil Bhubaneswar). The geographical coordinates are 20°22'55.10"N and 85°49'24.56"E. The site is adjacent to the Nandankanan Road on the east. A "dead canal" and a natural drain are located near the southern boundary of the plot.
Connectivity to the site is provided via NH-16 (6.3 km east) and NH-316 A (7.5 km east-southeast). The Bhubaneswar New Junction Railway Station is approximately 1.3 km away, and the Biju Patnaik International Airport is 13.5 km to the south.
Water, power and access
Water Supply
The total water requirement is estimated at 96 kilolitres per day (KLD). During the operation phase, the primary source will be groundwater. Domestic demand accounts for 94 KLD, while 3 KLD is required for horticulture. The applicant plans to use 61 KLD of fresh water and 32 KLD of recycled water for flushing.
An onsite Sewage Treatment Plant (STP) with a capacity of 112 KLD using Moving Bed Biofilm Reactor (MBBR) technology will be installed. It is expected to generate 81 KLD of wastewater, which will be treated and reused for flushing and horticulture. Surplus treated effluent (38 to 40 KLD depending on the season) will be discharged into the municipal sewer.
Power and Backup
The maximum power demand is estimated at 1,498.82 kVA, to be supplied by TP Central Odisha Distribution Limited (TPCODL). The applicant proposes to meet 5% of this demand through solar energy (74.941 kVA). For emergency backup, one diesel generator (DG) set of 1,010 kVA capacity will be installed, equipped with acoustic enclosures and a stack height designed according to environmental norms.
Environmental safeguards
Waste Management
During operation, the project is expected to generate approximately 365 kg of solid waste per day. This includes 335 kg from residents and 30 kg from staff and visitors. The applicant plans to use an organic waste converter to treat biodegradable waste into manure for landscaping. Recyclable materials will be sold to authorized vendors.
Rainwater Harvesting
The project includes one rainwater harvesting pit with a capacity of 75 cubic metres. The system is designed to handle a peak hourly rainfall of 65 mm/hr. Roof-top runoff will be collected and filtered before being used for groundwater recharge.
Greenery
The proposed green area of 697.25 square metres will feature 60 trees. Planned species include Jarul, Ashoka, Jackfruit, Shirish, and Neem, among others. A peripheral green belt will be developed to act as a noise and dust buffer.
NAWAH Corporate Residential Apartment Project "9 Emporio" site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
167 applications in Khordha since January 2022 are in the same category (Buildings & townships): 103 approved, 31 filed or under review, and 32 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 1 acre, this one is smaller than 96% of them.
33 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Raghunathpur, Nandankanan, Khordha, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Environment Clearance of Proposed (B+G+18) Storied MIG Residential Apartment… — environmental approval granted, 150 m away
- Revision & Expansion of Multi Storied Residential Project by M/s Uditi… — environmental approval granted, 250 m away
- Mixed use Project by M/s Utkal Subhalabha LLP — environmental approval granted, 700 m away
- Residential Project "royal Presidency" by Sjd- Presidency Homes LLP — environmental approval granted, 800 m away
- Expansion in Residential Apartment project "9 Boulevard" at Nandankanan Road,… — environmental approval granted, 850 m away
- Group Housing Project "Evos Alchemy" — environmental approval granted, 1.4 km away
- Group Housing Project "Evos Alchemy" — cleared for impact study, 1.4 km away
- Residential Apartment (Mani Tribhuvan Phase II) at Mouza- Kalarahanga,… — environmental approval granted, 1.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.