| Official title | Proposed installation of 0.12 Million TPA(Throughput) Chrome Ore beneficiation Plant at mouza Baragada of G.P-Paria, Tahasil- Darpan, Dist.-Jajpur by M/s Mother Resources & Co. |
|---|---|
| Status | Environmental approval granted |
| Status since | 15 Oct 2025 |
| Application filed | 2 Aug 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Mother Resources & Co |
| Land area | 3.3 acres (1.3 ha) |
| Project cost | ₹9.9 crore |
| Village / locality | Paria |
| Taluk / tehsil | Badachana |
| District | Jajapur |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-01973 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 2 Aug 2025 (this page) | Environmental approval granted | 3.3 acres | ₹9.9 crore |
| Early planning filed 1 Mar 2024 | Cleared for impact study | 3.3 acres | ₹9.9 crore |
In context
214 applications in Jajapur since January 2022 are in the same category (Mining): 131 approved, 18 filed or under review, and 65 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 3.3 acres, this one is smaller than 88% of them.
No other mining lease on record is within 500 m of this site; 3 have applied within 5 km.
Where it is
Paria, Badachana, Jajapur, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 0.12 Million TPA(Throughput) Chrome Ore beneficiation Plant at mouza Baragada… — cleared for impact study, 0 m away
- Expansion of Chrome Ore Beneficiation Unit form throughput capacity of 18500… — under environmental review, 3.4 km away
- Lahandabud Sand Mining Cluster constitute of Lahandabud B and Lahandabud C… — lapsed, 3.4 km away
- Expansion of Chrome Ore Beneficiation Unit form throughput capacity of 18500… — cleared for impact study, 3.4 km away
- Diversion of 0.259 Ha of forest land for construction (Temporary) of 33 KV… — lapsed, 3.9 km away
- Greenfield Project for installation of Cement Grinding Unit of capacity 3.0… — environmental approval granted, 4.1 km away
- Change in Configuration of Greenfield Project for Installation of Cement… — initial checks, 4.5 km away
- Approach Road to Byree Industrial Area. — under forest review, 4.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.