Quick answers
What is this project?
Proposed Industrial Building having total built up area 1,20,397.81 sqm over total plot area 100 Acres for establishment of 40,000 TPA of Titanium Dioxide Pigment plant, 1,20,000 TPA of Sulphuric Acid plant, 16,000 Nm3/Hr of Producer Gas plant, Brick plant of 40,000 Bricks/day, 4.8 MW of FBC based Co-generation Power Plant by M/s Shri Bajrang Power & Metallics Limited is a proposed building project in Sahaspur, Begunia, Khordha, Odisha. The site covers 100 acres.
Who is building it?
The applicant is Shri Bajrang Power &Metallics Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.
Where is it?
In Sahaspur, Begunia, Khordha, Odisha.
How big is it?
It has a stated cost of ₹1,275.5 crore and a site of 100 acres.
When was it filed?
The application was filed on 14 May 2025.
Project details
| Official title | Proposed Industrial Building having total built up area 1,20,397.81 sqm over total plot area 100 Acres for establishment of 40,000 TPA of Titanium Dioxide Pigment plant, 1,20,000 TPA of Sulphuric Acid plant, 16,000 Nm3/Hr of Producer Gas plant, Brick plant of 40,000 Bricks/day, 4.8 MW of FBC based Co-generation Power Plant at Village- Sahaspur, Tehsil-Bologarh, District Khorda, Odisha by M/s Shri Bajrang Power & Metallics Limited |
|---|---|
| Status | Returned to applicant |
| Status since | 26 Sept 2025 |
| Application filed | 14 May 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Shri Bajrang Power &Metallics Limited |
| Land area | 100 acres (40.5 ha) |
| Project cost | ₹1,275.5 crore |
| Village / locality | Sahaspur |
| Taluk / tehsil | Begunia |
| District | Khordha |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-02456 |
In context
167 applications in Khordha since January 2022 are in the same category (Buildings & townships): 103 approved, 31 filed or under review, and 32 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 100 acres, this one is larger than 98% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sahaspur, Begunia, Khordha, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Industrial Building having total built up area 1,20,397.81 sqm over… — returned to applicant, 0 m away
- Satellite Based Land Surface Temperature Anomalies Thermal Hot Spots… — lapsed, 2.3 km away
- Proposed Project for the Development of Integrated Textile Facilities for… — environmental approval granted, 8.5 km away
- Expansion of Refractory Manufacturing Plant by M/s Calderys India Refractories… — environmental approval granted, 8.6 km away
- Refractory Manufacturing Plant by M/s Calderys India Refractories Limited — environmental approval granted, 8.6 km away
- Reconsideration of Environmental Clearance (EC) for Srichandanpur Boulder… — not approved, 11.7 km away
- Obtaining Grant of Ec of Srichandanpur Boulder Quarry Over an Area of 4.625… — under environmental review, 11.7 km away
- Obtaining Grant of Ec of Srichandanpur Boulder Quarry Over an Area of 4.625… — not approved, 11.8 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.