Quick answers
What is this project?
Submission of Replenishment Study Report of Paika River Sand Quarry Over an area of 7.55 Acres or 3.055 Hectares is an approved mining project in Gandhan Pada, Tirtol, Jagatsinghapur, Odisha. The site covers 7.6 acres.
Who is building it?
The applicant is Satyabrata Pattnaik.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 16 Jun 2025), as of 27 Nov 2026.
Where is it?
In Gandhan Pada, Tirtol, Jagatsinghapur, Odisha.
How big is it?
It has a stated cost of ₹5 lakh and a site of 7.6 acres.
When was it filed?
The application was filed on 10 Mar 2025.
Project details
| Official title | Submission of Replenishment Study Report of Paika River Sand Quarry Over an area of 7.55 Acres or 3.055 Hectares in Village Gobardhanpur under Kujang Tahasil of Jagatsinghpur District, Odisha. |
|---|---|
| Status | Environmental approval granted |
| Status since | 16 Jun 2025 |
| Application filed | 10 Mar 2025 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Mining |
| Applicant | Satyabrata Pattnaik |
| Land area | 7.6 acres (3.1 ha) |
| Project cost | ₹5 lakh |
| Village / locality | Gandhan Pada |
| Taluk / tehsil | Tirtol |
| District | Jagatsinghapur |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-02671 |
In context
48 applications in Jagatsinghapur since January 2022 are in the same category (Mining): 34 approved, 5 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 7.6 acres, this one is smaller than 72% of them.
No other mining lease on record is within 500 m of this site; 7 have applied within 5 km.
Where it is
Gandhan Pada, Tirtol, Jagatsinghapur, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Amendment of Environmental Clearance of Anupala Paikanadi Sand Sairat Over an… — environmental approval granted, 2.2 km away
- Fresh EC of Anupala Paikanadi Sand Sairat over an area of 12.35 Acres or 4.99… — environmental approval granted, 2.2 km away
- Paika River Sand Quarry — environmental approval granted, 2.3 km away
- Paika River Sand Quarry over an area of 12.35 acres or 4.997 hectares — environmental approval granted, 2.3 km away
- Bilashpur Paika Nadi Sand Quarry Over an Area of 5.26hectares Under Tirtol… — more information requested, 2.3 km away
- Transfer TOR of Arilo-Jaipur Sand Sairat over an area of 13.00 acre or 5.26 Ha — cleared for impact study, 3.8 km away
- Amendment EC of Adhapati Paika Nadi Sand Bed over an area of 12.50 Acres or… — environmental approval granted, 4.6 km away
- Amendment EC of Olagada Tartol Mahanadi Sand Sairat over an area of 20.00… — initial checks, 5.4 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.