Submission of Replenishment Study Report (2024-25) for Amendment of Environment Clearance of Champrei River Sand Bed over an area of 12.30 Acres or 4.977 hectares is an approved mining project in Champarei, Rairangpur Town, Mayurbhanj, Odisha. The site covers 12.3 acres.
Who is building it?
The applicant is Tapas Das.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 14 Oct 2025), as of 27 Nov 2026.
Where is it?
In Champarei, Rairangpur Town, Mayurbhanj, Odisha.
How big is it?
It has a stated cost of ₹5 lakh and a site of 12.3 acres.
When was it filed?
The application was filed on 6 Aug 2025.
Project details
| Official title | Submission of Replenishment Study Report (2024-25) for Amendment of Environment Clearance of Champrei River Sand Bed over an area of 12.30 Acres or 4.977 hectares in Village Champrei under Rairangpur Tahasil of Mayurbhanj District of Odisha. In favour of Sri Tapas Kumar Das |
|---|---|
| Status | Environmental approval granted |
| Status since | 14 Oct 2025 |
| Application filed | 6 Aug 2025 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Mining |
| Applicant | Tapas Das |
| Land area | 12.3 acres (5 ha) |
| Project cost | ₹5 lakh |
| Village / locality | Champarei |
| Taluk / tehsil | Rairangpur Town |
| District | Mayurbhanj |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-03116 |
In context
150 applications in Mayurbhanj since January 2022 are in the same category (Mining): 74 approved, 15 filed or under review, and 61 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 12.3 acres, this one is smaller than 61% of them.
No other mining lease on record is within 500 m of this site; 6 have applied within 5 km.
Where it is
Champarei, Rairangpur Town, Mayurbhanj, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environment Clearance of Laxmiposi Sand Bed over an area of 12.35… — environmental approval granted, 1.6 km away
- Laxmiposi Sand Bed Over an area of 12.35 Acres or 4.99 hectares — environmental approval granted, 1.6 km away
- Ranipal Sand Bed over an area of 12.00 Acres or 4.856 hectares — environmental approval granted, 2.7 km away
- Ranipal Sand Bed Over an Area of 12.00 Acres Or 4.856 Hectares — environmental approval granted, 2.7 km away
- Extension of Validity Period of EC for Baghia Stone Quarry Over an area of… — not approved, 4.4 km away
- Baghia Stone Quarry Over an area of 4.92 Acre or 1.99 Hectares — environmental approval granted, 4.4 km away
- Ghumal Sand Bed Over an Area of 12.35 Acres Or 4.99 Hectares — environmental approval granted, 6.8 km away