What is this project?
Environment Clearance of proposed (2B+G+First+4P+Amenity+15) storied Commercial Building in Mouza-Chandrasekhar-41, Bhubaneswar, Dist-Khurda, Odisha is a proposed commercial project in Bhubaneshwar Town, Bhubaneswar (M.Corp.), Khordha, Odisha. It plans 1 tower of up to 15 floors on 2.4 acres.
Who is building it?
The applicant is Anuj Autogrph Business Park.
Has it been approved?
Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.
Where is it?
In Bhubaneshwar Town, Bhubaneswar (M.Corp.), Khordha, Odisha.
How big is it?
It has a stated cost of ₹160 crore and a site of 2.4 acres.
When was it filed?
The application was filed on 19 Jan 2026.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Environment Clearance of proposed (2B+G+First+4P+Amenity+15) storied Commercial Building…
Project details
| Status | Returned to applicant |
|---|---|
| Status since | 15 May 2026 |
| Application filed | 19 Jan 2026 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Buildings & townships |
| Applicant | Anuj Autogrph Business Park |
| Use | Commercial |
| Towers | 1 |
| Floors (tallest) | 15 |
| Basements | 2 |
| Height | 84 m |
| Parking spaces | 944 |
| Land area | 2.4 acres (1 ha) |
| Built-up area | 77,294 m² (8,31,985 sq ft) |
| Plot area | 9,648 m² (1,03,850 sq ft) |
| Project cost | ₹160 crore |
| Village / locality | Bhubaneshwar Town |
| Taluk / tehsil | Bhubaneswar (M.Corp.) |
| District | Khordha |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-03280 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 19 Jan 2026 (this page) | Returned to applicant | 2.4 acres | ₹160 crore |
| New project filed 3 Dec 2024 | Environmental approval granted | 2.4 acres | ₹160 crore |
In context
167 applications in Khordha since January 2022 are in the same category (Buildings & townships): 103 approved, 31 filed or under review, and 32 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 2.4 acres, this one is smaller than 72% of them.
57 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhubaneshwar Town, Bhubaneswar (M.Corp.), Khordha, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Environment Clearance of proposed (2B+G+First+4P+Amenity+15) storied… — environmental approval granted, 0 m away
- Expansion of Commercial Building 'Infinity Park' by M/s Anuj Autogrph Business… — environmental approval granted, 0 m away
- Environmental Clearance for Proposed (2B+G+7) Commercial-Cum-Multiplex… — environmental approval granted, 650 m away
- Environment Clearance of Proposed (B1+B2+G+15) Storied building for IT Park… — environmental approval granted, 950 m away
- Environment Clearance of Proposed (B1+B2+G+15) Storied building for IT Park… — environmental approval granted, 950 m away
- Environment clearance of "Residential Apartment" for M/s Kalvik Builders Pvt.… — under environmental review, 1.4 km away
- Environment Clearance of Proposed (2B+G+14) Multistoried I.T. Building for M/s… — environmental approval granted, 1.5 km away
- IT Park and Business Centre "Pine Square" — lapsed, 1.6 km away
More from Anuj Autogrph Business Park in Khordha
- Expansion of Commercial Building 'Infinity Park' by M/s Anuj Autogrph Business… — environmental approval granted
All 3 Anuj Autogrph Business Park projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.