Quick answers
What is this project?
Establishing "An Advanced Glass Substrate-Based Semiconductor Packaging and Manufacturing Unit", at IDCO Plot No. S1-IT-02, Rev Plot No. 255 (P), 258 (P) & 320/509 (P) Rev. Khata No. 166/87, Revenue Village: Goudakasipur, Dist: Khordha, Tahasil: Jatni, State: Odisha by M/s. Heterogenous Integration Packaging Solutions Private Limited over an area 10.1171 Ha (25 Acre) is an approved industrial building project in Gaudakashipur, Jatani, Khordha, Odisha. The site covers 25 acres.
Who is building it?
The applicant is HETEROgeNOUS INTEGRATION PACKAGING SOLUTIONS PRIVATE LIMITED.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 20 Jul 2026), as of 27 Nov 2026.
Where is it?
In Gaudakashipur, Jatani, Khordha, Odisha.
How big is it?
It has a stated cost of ₹1,861.9 crore and a site of 25 acres.
When was it filed?
The application was filed on 17 Jun 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 20 Jul 2026 |
| Application filed | 17 Jun 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | HETEROgeNOUS INTEGRATION PACKAGING SOLUTIONS PRIVATE LIMITED |
| Use | Industrial |
| Land area | 25 acres (10.1 ha) |
| Built-up area | 60,838 m² (6,54,854 sq ft) |
| Plot area | 1,01,170 m² (10,88,984 sq ft) |
| Project cost | ₹1,861.9 crore |
| Village / locality | Gaudakashipur |
| Taluk / tehsil | Jatani |
| District | Khordha |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-03288 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 17 Jun 2026 (this page) | Environmental approval granted | 25 acres | ₹1,861.9 crore |
| New project filed 23 Mar 2026 | Returned to applicant | 25 acres | ₹280.3 crore |
In context
167 applications in Khordha since January 2022 are in the same category (Buildings & townships): 103 approved, 31 filed or under review, and 32 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 25 acres, this one is larger than 86% of them.
16 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Gaudakashipur, Jatani, Khordha, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Establishing "An Advanced Glass Substrate-Based Semiconductor Packaging and… — returned to applicant, 0 m away
- Construction Proposed Academic Cum Administrative Office Building and Proposed… — more information requested, 250 m away
- Diversion of 0.494 Ha of Revenue Forest Land for Establishment of Data Center… — forest land use approved, 1.1 km away
- Environment Clearance for Proposed Addition and Alternation on G+1 (OPD Block,… — environmental approval granted, 1.1 km away
- Environmental Clearance of Compound Semiconductor FAB and ATMP (Assembly,… — environmental approval granted, 1.2 km away
- RBI Greenfield data center and enterprise level Training institute at IDCO… — environmental approval granted, 1.2 km away
- RBI Greenfield data center and enterprise level Training institute at IDCO… — environmental approval granted, 1.2 km away
- Environmental Clearance of Addition and alternation of (S+6) Multi Storied… — more information requested, 1.5 km away
About this information