What is this project?
Fresh Ec of Jadatira Brick Earth Quarry Over an Area of 1.89 Acres Or 0.764 Ha is a rejected mining project in Tirtol, Jagatsinghapur, Odisha. The site covers 0.7 acres.
Who is building it?
The applicant is Bijay Nath.
Has it been approved?
No. The application was rejected on 14 May 2026.
Where is it?
In Tirtol, Jagatsinghapur, Odisha.
How big is it?
It has a stated cost of ₹20 lakh and a site of 0.7 acres.
When was it filed?
The application was filed on 21 Feb 2026.
Project details
| Official title | Proposal for Fresh Ec of Jadatira Brick Earth Quarry Over an Area of 1.89 Acres Or 0.764 Ha at Village-Jadatira, Tahasil-Tirtol, District-Jagatsinghpur, Odisha of M/S. Durga Bricks, Prop-Sri Bijay Kumar Nath |
|---|---|
| Status | Not approved |
| Status since | 14 May 2026 |
| Application filed | 21 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Bijay Nath |
| Land area | 2,900 m² |
| Project cost | ₹20 lakh |
| Village / locality | Tirtol |
| Taluk / tehsil | Tirtol |
| District | Jagatsinghapur |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-03842 |
In context
48 applications in Jagatsinghapur since January 2022 are in the same category (Mining): 34 approved, 5 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 0.7 acres, this one is smaller than 100% of them.
2 other mining leases have applied within 500 m of this site; together with this one they cover 2.8 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 12 mining leases have applied within 5 km.
Where it is
Tirtol, Jagatsinghapur, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Grant of Environment Clearance of M/s Durga Brick Earth Quarry over an area of… — environmental approval granted, 350 m away
- Fresh Ec of Jadatira Brick Earth Quarry Over an Area of 1.19 Acres Or 0.481… — environmental approval granted, 350 m away
- Fresh Ec of M/S. Sarada K.B Brick Earth Quarry Over an Area of 2.56 Acres Or… — environmental approval granted, 850 m away
- Water Treatment Plant (WTP) for execution of Rural Piped Water Supply Project… — in-principle approval, conditions pending, 900 m away
- Fresh Ec of Tirtol Brick Earth Quarry Over an Area of 2.56 Acres Or 1.036 Ha — not approved, 1 km away
- FRESH EC OF TIRTOL BRICK EARTH QUARRY OVER AN AREA OF 1.29 ACRES OR 0.522… — environmental approval granted, 1.1 km away
- Amendment EC of Olagada Tartol Mahanadi Sand Sairat over an area of 20.00… — initial checks, 1.3 km away
- Amendment EC of Olagada Tartol Mahanadi Sand Sairat over an area of 20.00… — lapsed, 1.3 km away
More from Bijay Nath in Jagatsinghapur
- Grant of Environment Clearance of M/s Durga Brick Earth Quarry over an area of… — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.