Quick answers
What is Mahaparbat (Unchabali) Iron Ore Mine?
Mahaparbat (Unchabali) Iron Ore Mine is a proposed mining project in Balada, Bamebari, Kendujhar, Odisha. The site covers 168 acres.
Who is building it?
The applicant is Odisha Mining Corporation Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Balada, Bamebari, Kendujhar, Odisha.
How big is it?
It has a stated cost of ₹287.1 crore and a site of 168 acres.
When was it filed?
The application was filed on 3 Nov 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 3 Nov 2026 |
| Application filed | 3 Nov 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Odisha Mining Corporation Limited |
| Land area | 168 acres (68 ha) |
| Project cost | ₹287.1 crore |
| Village / locality | Balada |
| Taluk / tehsil | Bamebari |
| District | Kendujhar |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-04888 |
In context
213 applications in Kendujhar since January 2022 are in the same category (Mining): 110 approved, 46 filed or under review, and 57 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 168 acres, this one is larger than 61% of them.
No other mining lease on record is within 500 m of this site; 12 have applied within 5 km.
Where it is
Balada, Bamebari, Kendujhar, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 22.368 Ha of Forest Land for 33 KV Power Transmission Line From… — initial checks, 900 m away
- Diversion of 0.469 Ha of Non-Forest Land Recorded As Forest As on 25.10.1980… — lapsed, 1.2 km away
- BHJ/BHQ Beneficiation Plant of 4 MTPA Throughput Capacity in Unchabali Iron… — lapsed, 1.2 km away
- Application for Change in Land Use Pattern Over an Area of 43.281 Ha. From… — not approved, 1.3 km away
- BHJ/BHQ Beneficiation Plant of 4 MTPA Throughput Capacity in Unchabali Iron… — cleared for impact study, 1.3 km away
- Preparation of Proposed Approach Road From Unchabali Iron & Manganese Mines of… — lapsed, 1.5 km away
- Nayagarh Iron Ore Mines — forest land use approved, 2.4 km away
- Nayagarh Iron Ore Mines — environmental approval granted, 2.4 km away
More from Odisha Mining Corporation Limited in Kendujhar
- Daitari Iron Ore Mine — lapsed
- Jilling Langalotta Iron Ore Mine — lapsed
- Expansion of Iron Ore Production Capacity From 0.328 Million Tpa to 0.995… — environmental approval granted
- Gandhmardan Iron Ore Mining Project — environmental approval granted
- Katupali Iron Ore Block — lapsed
- Gandhamardan Iron Ore Mining Project — returned to applicant
15 Odisha Mining Corporation projects in Kendujhar
All 41 Odisha Mining Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.