| Status | Under environmental review |
|---|---|
| Status since | 13 Nov 2026 |
| Application filed | 13 Nov 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Rungta Sons Private Limited |
| Land area | 516.9 acres (209.2 ha) |
| Project cost | ₹150 crore |
| Village / locality | Batagaon |
| Taluk / tehsil | Lahunipara |
| District | Sundargarh |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-04918 |
In context
310 applications in Sundargarh since January 2022 are in the same category (Mining): 161 approved, 55 filed or under review, and 94 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 516.9 acres, this one is larger than 82% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 1,566.2 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 5 mining leases have applied within 5 km.
Where it is
Batagaon, Lahunipara, Sundargarh, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 211.764 Ha(209.166 Ha. Lease Area + 2.598 Ha. for Connecting Road… — not approved, 0 m away
- Jumka Pathiriposhi Pahar Iron Ore Block — environmental approval granted, 1000 m away
- Exploration proposal at Sub-Block-E (Khandadhar East) — lapsed, 2.1 km away
- Diversion of 100.797 Ha.(100.439 Ha Lease Area + 0.358 Ha. for Connecting Road… — in-principle approval, conditions pending, 2.6 km away
- Environment Clearance for Kedesala North East Iron Ore Block for production of… — environmental approval granted, 2.6 km away
- Environment Clearance for Kedesala North East Iron Ore Block for production of… — cleared for impact study, 2.6 km away
- Production of 2.0 Mtpa Iron Ore by Kashvi Power & Steel LTD — lapsed, 4.9 km away
- Khandadhar Sub-Block-C — more information requested, 5.2 km away
More from Rungta Sons Private Limited in Sundargarh
- Diversion of 211.764 Ha(209.166 Ha. Lease Area + 2.598 Ha. for Connecting Road… — not approved
- Proposed Expansion of the Integrated Project of Iron Ore Beneficiation Plant… — under environmental review
- Environmental Clearance for proposed 12 MTPA (3 nos x 3 MTPA + 2 nos x 1.5… — environmental approval granted
- Diversion of 3.119 Ha Forest Land for Construction of Approach Road and… — more information requested
- Environmental Clearance for proposed 12 MTPA (3 nos x 3 MTPA + 2 nos x 1.5… — cleared for impact study
- Mahulasukha Iron and Manganese Block over an area of 390.317 Ha — cleared for impact study
11 Rungta Sons projects in Sundargarh
All 40 Rungta Sons projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.