Quick answers
What is this project?
"Integrated Manufacturing Cluster" by M/s Punjab Urban Planning & Development Authority (PUDA) is an approved industrial project in Abdalpur, Rajpura, Patiala, Punjab. The site covers 8,680.9 acres.
Who is building it?
The applicant is Industrial Manufacturing Cluster (Imc), Rajpura by Puda.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 17 Jun 2025), as of 27 Nov 2026.
Where is it?
In Abdalpur, Rajpura, Patiala, Punjab.
How big is it?
It has a stated cost of ₹1,367.7 crore and a site of 8,680.9 acres.
When was it filed?
The application was filed on 19 Feb 2025.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 17 Jun 2025 |
| Application filed | 19 Feb 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Industrial Manufacturing Cluster (Imc), Rajpura by Puda |
| Land area | 8,680.9 acres (3,513 ha) |
| Project cost | ₹1,367.7 crore |
| Village / locality | Abdalpur |
| Taluk / tehsil | Rajpura |
| District | Patiala |
| State | Punjab |
| Location from | Site boundary on record |
| Our reference | WID-PB-00061 |
In context
45 applications in Patiala since January 2022 are in the same category (Industry): 29 approved, 6 filed or under review, and 10 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 8,680.9 acres, this one is larger than 98% of them.
Where it is
Abdalpur, Rajpura, Patiala, Punjab. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Amendment in the existing EC granted to the Steel Manufacturing Unit of M/s… — environmental approval granted, 27.7 km away
- Transfer of Environmental Clearance from M/s Madhav Alloys Pvt. Ltd. to M/s… — environmental approval granted, 28 km away
- Amendment in the EC granted vide no. DECC/SEIAA/2020/1656 dated 20/05/2020 of… — lapsed, 28 km away
- Permission for construction of approach Access to Proposed Hotel Blue Heaven — forest land use approved, 30.1 km away
- NOC Regarding New Construction of Rani Dhee Mandir to Agoul Mallehwal Road… — more information requested, 32.7 km away
- NOC Regarding New Construction of Rani Dhee Mandir to Agoul Mallehwal Road… — more information requested, 32.7 km away
- New Construction of Rani Dhee Mandir to Agoul Mallehwal Road L 2.90 Km. — application filed, 32.7 km away
- Permission of forest land for construction of approach Access to KARTAR AGRO… — forest land use approved, 32.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.