Project details
| Official title | Residential Project Namely "Silver City Themes" Located At Village Bhankharpur, Tehsil Dera Bassi, SAS Nagar Punjab By M/S Silver City Housing And Infrastructure Limited. |
|---|---|
| Status | Environmental approval granted |
| Status since | 1 Feb 2024 |
| Application filed | 4 Jan 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Silver City Housing and Infrastructure Limited |
| Use | Residential |
| Units | 1,030 |
| Land area | 14 acres (5.7 ha) |
| Built-up area | 1,27,396 m² (13,71,278 sq ft) |
| Plot area | 56,614 m² (6,09,387 sq ft) |
| Project cost | ₹239 crore |
| Village / locality | Bhankharpur |
| Taluk / tehsil | Dera Bassi |
| District | Sahibzada Ajit Singh Nagar (Mohali) |
| State | Punjab |
| Location from | Site boundary on record |
| Our reference | WID-PB-00180 |
What the filings say
What is planned
Silver City Housing and Infrastructure Limited is expanding its existing residential housing project, "Silver City Themes," in Bhankharpur. The applicant's conceptual plan states that the project is being expanded by adding two towers to the existing development. Upon completion, the project will comprise a total of 1,030 flats across five towers.
The total built-up area after expansion will be 1,27,395.86 square metres. The housing units are categorized as follows:
- 2/3 BHK Flats: 940 units
- 1 BHK / EWS (Economically Weaker Section) Flats: 90 units
Layout and design
The project is situated on a plot area of 56,614.331 square metres (approximately 13.99 acres). The expansion does not involve any increase in the plot area. The achieved Floor Area Ratio (FAR) is 1:2.142. The ground coverage is 18,230.697 square metres, which represents 32.19% of the plot, staying within the permissible limit of 35%.
Traffic within the premises is designed to be one-way with separate entry and exit gates. The project provides a total of 520 Equivalent Car Spaces (ECS), consisting of 339 surface parking spots and 181 basement parking spots.
Water, power and access
The total water requirement for the project after expansion is estimated at 672 kilolitres per day (KLD). Of this, the domestic fresh water demand is approximately 448 KLD, while 224 KLD will be met through recycled water for flushing. Waste water generation is estimated at 538 KLD.
The project site is connected to the Dera Bassi Ramgarh Road. For power, the total load is estimated at 4,955 KW. The applicant proposes to save 17% of energy (750 KW) through the use of LED lighting, solar energy for outer lighting, and rooftop solar panels with a 500 KW capacity. For power backup, four 250 KVA diesel generator (DG) sets are already installed, and six 600 KVA DG sets are planned for installation.
Environmental safeguards
A Sewage Treatment Plant (STP) with a capacity of 750 KLD is already installed and operational on-site. Treated water will be used for flushing, tree plantation, and landscaping. The project generates approximately 2,240.25 kg of municipal solid waste per day, which will be segregated into bio-degradable (50%), recyclable (45%), and inert waste (5%). Bio-degradable waste is to be treated through vermi-composting.
For rain water harvesting, two recharge pits have already been constructed, and 12 more are planned, bringing the total to 14 pits. The green belt will cover the project area with a plan to plant 708 trees; 300 plants have already been planted. Species selected include Arjun, Baheda, Neem, Pilkin, and Gulmohar.
| Item | Detail |
|---|---|
| Total Built-up Area | 1,27,395.86 sqm |
| Total Flats | 1,030 units |
| Total Water Requirement | 672 KLD |
| STP Capacity | 750 KLD |
| Total Power Load | 4,955 KW |
| Total Parking (ECS) | 520 |
| Solid Waste Generated | 2,240.25 kg/day |
| Rain Water Recharge Pits | 14 (Total) |
| Proposed Tree Plantation | 708 plants |
Residential Project Namely "Silver City Themes" site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
384 applications in Mohali since January 2022 are in the same category (Buildings & townships): 276 approved, 60 filed or under review, and 48 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 14 acres, this one is larger than 73% of them.
101 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhankharpur, Dera Bassi, Mohali, Punjab. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- M/s Punjab Chemicals and Crop Protection Ltd. (Agro-Division), located at… — initial checks, 750 m away
- Expansion in Existing API Manufacturing Industrial Unit "Without increase in… — initial checks, 800 m away
- API manufacturing industrial unit namely "M/s Synthimed Labs Private Limited"… — environmental approval granted, 800 m away
- Expansion in Existing API Manufacturing Industrial Unit located at Plot nos.… — returned to applicant, 850 m away
- Expansion in Existing API Manufacturing Industrial Unit located at Plot nos.… — cleared for impact study, 850 m away
- The Regiment — under environmental review, 1.1 km away
- Elfinia — withdrawn, 1.1 km away
- Etherea Height — lapsed, 1.1 km away