Environmental approval grantedBuildings & townships · Sahibzada Ajit Singh Nagar, Punjab

The Regiment

The Regiment is an approved residential project in Dera Bassi, Mohali, Punjab. It plans 338 units on 3.1 acres. Its stated project cost is ₹65 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 18 Jun 2026).

See it on the live map All projects in Sahibzada Ajit Singh Nagar

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusEnvironmental approval granted
Status since18 Jun 2026
Application filed8 Sept 2025
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantEvermark Building Innovations Private Limited
UseResidential
Units338
Parking spaces477
Land area3.1 acres (1.3 ha)
Built-up area42,347 m² (4,55,819 sq ft)
Plot area12,717 m² (1,36,885 sq ft)
Project cost₹65 crore
Village / localityDera Bassi
Taluk / tehsilDera Bassi
DistrictSahibzada Ajit Singh Nagar (Mohali)
StatePunjab
Location fromSite area on record
Our referenceWID-PB-00901

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Amendment filed 23 Sept 2026Under environmental review3.1 acres₹65 crore
New project filed 8 Sept 2025 (this page)Environmental approval granted3.1 acres₹65 crore

What the filings say

What is planned

The Regiment is a group housing project proposed by Evermark Building Innovations Private Limited. The applicant received environmental clearance in June 2026 for a built-up area of 42,347 square metres. In September 2026, the applicant filed for an amendment to increase the built-up area to 50,146 square metres, citing an increase in non-FAR (Floor Area Ratio) basement area from 883 square metres to 8,682 square metres.

The residential component consists of 338 flats across several blocks. The unit configuration includes:

Supporting components include a commercial centre of 366 square metres and a shop area of 412 square metres containing six shops. The total estimated population for the project is 2,636 persons, comprising 1,912 residents, 398 commercial/shop staff and visitors, and 326 floating population.

Layout and design

The project is planned on a net area of 1.27 hectares (3.14 acres). The layout includes multiple residential towers (Blocks A through F), a community centre, and a dedicated shop block. The achieved ground coverage is 4,208.98 square metres. Parking facilities are designed to accommodate 477 Equivalent Car Spaces (ECS).

Water, power and access

The total water demand during the operation phase is estimated at 277 kilolitres per day (KLD), with a fresh water requirement of 180 KLD. Wastewater generation is projected at 222 KLD, which will be treated in an on-site Sewage Treatment Plant (STP) with a capacity of 350 KLD using Sequential Batch Reactor (SBR) technology followed by Ultra Filtration (UF). The treated water will be reused for flushing (97 KLD) and horticulture (2 to 20 KLD depending on the season), with the surplus discharged into the municipal sewer.

Power requirements are estimated at 2,500 KW, to be sourced from Punjab State Power Corporation Limited (PSPCL). For backup, the applicant proposes to install three Diesel Generator (DG) sets: one 240 KVA unit and two 125 KVA units. Energy-saving measures include the use of LED lamps for common areas and 30 solar street lights.

Environmental safeguards

The applicant plans to develop 3,617 square metres of green area, which exceeds the required 3,179 square metres. This includes the plantation of 190 indigenous tree saplings. For rainwater management, seven recharging pits are proposed.

Solid waste generation is estimated at 1,005 kg per day. The applicant intends to install a mechanical composter with a capacity of 550 kg per day to process wet waste. A Material Recovery Facility (MRF) covering 300 square metres and a baling machine for dry waste will also be established. The project aims for a "Zero Waste to Landfill" status by segregating waste at the source and partnering with authorized recyclers for dry and hazardous waste disposal.

ItemDetail
Total Plot Area12,717 sqm (1.27 hectares)
Total Built-up Area (Proposed)50,146 sqm
Total Residential Units338 Flats
Estimated Population2,636 Persons
STP Capacity350 KLD
Total Solid Waste1,005 kg/day
Power Load2,500 KW
Parking Provided477 ECS
Green Area3,617 sqm

The Regiment site plan and layout

2 drawings from the project's filings. Sign in free to see them.

The Regiment: Site plan and block layouts: residential towers, community center, and shops (preview)🔒 Sign in free to see it
Site plan and block layouts: residential towers, community center, and shops
The Regiment: Amendment table: comparison of original and proposed built-up areas (preview)🔒 Sign in free to see it
Amendment table: comparison of original and proposed built-up areas

In context

384 applications in Mohali since January 2022 are in the same category (Buildings & townships): 276 approved, 60 filed or under review, and 48 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 3.1 acres, this one is smaller than 82% of them.

87 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Dera Bassi, Mohali, Punjab. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Evermark Building Innovations Private Limited in Sahibzada Ajit Singh Nagar

All 3 Evermark Building Innovations projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.