Project details
| Official title | Area Development Project namely "Ecocity 3" at Village Rasulpur, Salamatpur, Dhode Majra, Takipur, Rajgarh, Majra, Kartarpur, Kansala and Hoshiarpur, New Chandigarh, Distt. S.A.S Nagar, Punjab |
|---|---|
| Status | Cleared for impact study |
| Status since | 8 Jul 2026 |
| Application filed | 14 May 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Buildings & townships |
| Applicant | Greater Mohali Area Development Authority |
| Use | Township |
| Land area | 716.1 acres (289.8 ha) |
| Built-up area | 40,94,367 m² (4,40,71,357 sq ft) |
| Plot area | 40,94,367 m² (4,40,71,357 sq ft) |
| Project cost | ₹587.5 crore |
| Village / locality | Hoshiarpur |
| Taluk / tehsil | Kharar |
| District | Sahibzada Ajit Singh Nagar (Mohali) |
| State | Punjab |
| Location from | Site boundary on record |
| Our reference | WID-PB-01112 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 25 Aug 2026 | Environmental approval granted | 716.1 acres | ₹587.5 crore |
| Early planning filed 14 May 2026 (this page) | Cleared for impact study | 716.1 acres | ₹587.5 crore |
In context
384 applications in Mohali since January 2022 are in the same category (Buildings & townships): 276 approved, 60 filed or under review, and 48 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 716.1 acres, this one is larger than 99% of them.
55 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Hoshiarpur, Kharar, Mohali, Punjab. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Area Development Project namely "Ecocity 3" — environmental approval granted, 0 m away
- Area development Project namely "Ecocity Phase -2" by M/s Greater Mohali Area… — lapsed, 1.2 km away
- M/S Hindustan Petroleum Corporation LTD. for Approach Road to Setting Up a New… — forest land use approved, 1.3 km away
- Opus One — environmental approval granted, 1.5 km away
- Opus One — cleared for impact study, 1.5 km away
- Opus One — environmental approval granted, 1.5 km away
- Diversion of 0.3786 ha. of forest land (0.3786 ha. Area of village Hoshiarpur)… — lapsed, 1.7 km away
- Proposed Township Project namely "Eco City Phase-2 Extension" by M/s Greater… — environmental approval granted, 1.9 km away
More from Greater Mohali Area Development Authority in Sahibzada Ajit Singh Nagar
- Industrial Estate by Greater Mohali Area Development Authority at Sector 83 &… — more information requested
- Area development Project namely "Ecocity Phase -2" by M/s Greater Mohali Area… — lapsed
- Industrial Estate by Greater Mohali Area Development Authority at Sector 83 &… — cleared for impact study
- Area Development Project namely "Low Density and High End Residential Apartment" — more information requested
- Area Development Project namely "Low Density and High End Residential Apartment" — lapsed
All 7 Greater Mohali Area Development Authority projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.