Erection of 11 kV feeder for New (NRS) Connection (Load 2160 kW / 2400 kWA) from PM E-Bus Sewa RID No. 169780 (Patiala Kedar Nath Depot) is a proposed power project in Patiala, Punjab. The site covers 0.1 acres.
Who is building it?
The applicant is Punjab State Power Corporation Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Patiala, Punjab.
How big is it?
It has a stated cost of ₹71 lakh; a site of 0.1 acres and 380 m² of forest land.
When was it filed?
The application was filed on 29 Oct 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 25 Nov 2026 |
| Application filed | 29 Oct 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Punjab State Power Corporation Limited |
| Land area | 400 m² |
| Forest land | 380 m² |
| Project cost | ₹71 lakh |
| Village / locality | Patiala |
| Taluk / tehsil | Patiala |
| District | Patiala |
| State | Punjab |
| Location from | Site boundary on record |
| Our reference | WID-PB-03722 |
In context
56 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Patiala, Punjab. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Laying of 160 mm O/D SN-8 UPVC Pipe for Sewerage system from E-Bus charging… — initial checks, 100 m away
- Permission for construction of approach Access to " The Business Central" of… — lapsed, 1.3 km away
- Rectification of 3 various Chowk in Patiala City Distt: Patiala under Forest… — forest land use approved, 1.4 km away
- Diversion of 0.0803 ha of forest land construction of approach access to… — more information requested, 1.5 km away
- Permission for construction of approach Access Retail Outlet Of Bharat… — forest land use approved, 1.5 km away
- Permission of forest land construction of approach access to Showroom of… — forest land use approved, 1.6 km away
- Permission of forest land construction of approach access to Commercial… — under forest review, 1.8 km away
- Approach access to Fish Market — lapsed, 1.9 km away
All 5 Punjab State Power Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.