Quick answers
What is this project?
Terms of Reference (TOR) for Granite Mining Project, ML. No.-11/2023, ML Area: 1.53602 Hectare. at Khasra No.- 4627, 4627/5407, 4628, 4650, 4651, 4652, 4653, Near Village-Baghera, Tehsil- Kekri, District- Ajmer (Raj.) of M/s Jain Granite is a proposed mining project in Baghera, Kekri, Ajmer, Rajasthan. The site covers 3.8 acres.
Who is building it?
The applicant is Jain Granite.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 1 Sept 2023), as of 27 Nov 2026.
Where is it?
In Baghera, Kekri, Ajmer, Rajasthan.
How big is it?
It has a stated cost of ₹4.2 crore and a site of 3.8 acres.
When was it filed?
The application was filed on 1 Sept 2023.
Project details
| Official title | Proposal for Terms of Reference (TOR) for Granite Mining Project, ML. No.-11/2023, ML Area: 1.53602 Hectare. at Khasra No.- 4627, 4627/5407, 4628, 4650, 4651, 4652, 4653, Near Village-Baghera, Tehsil- Kekri, District- Ajmer (Raj.) of M/s Jain Granite |
|---|---|
| Status | Cleared for impact study |
| Status since | 1 Sept 2023 |
| Application filed | 1 Sept 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Jain Granite |
| Land area | 3.8 acres (1.5 ha) |
| Project cost | ₹4.2 crore |
| Village / locality | Baghera |
| Taluk / tehsil | Kekri |
| District | Ajmer |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-01059 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 15 Jul 2025 | Lapsed | 3.8 acres | ₹4.2 crore |
| Early planning filed 1 Sept 2023 (this page) | Cleared for impact study | 3.8 acres | ₹4.2 crore |
In context
1,559 applications in Ajmer since January 2022 are in the same category (Mining): 904 approved, 102 filed or under review, and 553 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 3.8 acres, this one is smaller than 56% of them.
8 other mining leases have applied within 500 m of this site; together with this one they cover 33.5 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 64 mining leases have applied within 5 km.
Where it is
Baghera, Kekri, Ajmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Terms of Reference (TOR) for Granite Mining Project, ML. No.-11/2023, ML Area:… — lapsed, 0 m away
- Granite Mining Project, M. L. No. 117/2021 — cleared for impact study, 150 m away
- M/s Pitambara Granite, M.L. NO. 94/2021,GRANITE MINING PROJECT — lapsed, 250 m away
- M/s Pitambara Granite, M.L. NO. 94/2021,GRANITE MINING PROJECT — more information requested, 250 m away
- Granite (Minor Mineral) mining project by M/s Shree Shyam Granite — lapsed, 250 m away
- Granite (Minor Mineral) mining project by M/s Shree Shyam Granite — cleared for impact study, 250 m away
- Cluster No 85. Nayagaon Granite Mining Project, ML. No. 15/2022, Applied Area.… — environmental approval granted, 400 m away
- M/s Paramount Minerals [Granite (Minor Mineral) Mining Project" Plot No. 86,… — environmental approval granted, 400 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.