Onshore Development Drilling & Production (25nos.Wells), Production Installations (02 Nos.) is an approved mining project in 32 Cwb, Kolayat, Bikaner, Rajasthan. The site covers 52,460 acres.
Who is building it?
The applicant is Oil India LTD Rajasthan Project.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 3 Jan 2025), as of 27 Nov 2026.
Where is it?
In 32 Cwb, Kolayat, Bikaner, Rajasthan.
How big is it?
It has a stated cost of ₹795 crore and a site of 52,460 acres.
When was it filed?
The application was filed on 7 Mar 2024.
Project details
| Official title | Onshore Development Drilling & Production (25nos.Wells), Production Installations (02 Nos.) With Associated Facilities in 210 Sq.Km Baghewala Pml Block |
|---|---|
| Status | Environmental approval granted |
| Status since | 3 Jan 2025 |
| Application filed | 7 Mar 2024 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Mining |
| Applicant | Oil India LTD Rajasthan Project |
| Land area | 52,460 acres (21,229.9 ha) |
| Project cost | ₹795 crore |
| Village / locality | 32 Cwb |
| Taluk / tehsil | Kolayat |
| District | Bikaner |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-01986 |
In context
516 applications in Bikaner since January 2022 are in the same category (Mining): 270 approved, 60 filed or under review, and 186 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 52,460 acres, this one is larger than 99% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
32 Cwb, Kolayat, Bikaner, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Onshore Developmental drilling & production from 85 no.s of wells in… — cleared for impact study, 500 m away
- "Construction of Ramgarh -Bhadla-III 765 KV D/C Transmission Line in… — forest land use approved, 37.7 km away
- Re Appraisal of EC Granted from DEIAA, Bikaner, of "Gypsum (Minor Mineral)… — lapsed, 45.3 km away
- "Construction for LILO of Circuit-II of 220kV D/C Bikampur-Kolayat… — more information requested, 55.7 km away
- "Laying of Underground Optical Fiber Cable Along the Road from… — more information requested, 55.7 km away
- Proposed Project of Bajri, Gravel, Murrum & Fuller's Earth, Mining Project… — lapsed, 55.9 km away
- Re Appraisal of EC granted by DEIAA, Bikaner (Rajasthan), of Existing Gypsum… — lapsed, 56.6 km away
- Re Appraisal of EC Granted from DEIAA, Bikaner, of "Gypsum (Minor Mineral)… — lapsed, 56.8 km away
More from Oil India LTD Rajasthan Project in Bikaner
- Proposed Onshore Exploratory drilling of 5 no.s of wells in OALP-V Block… — environmental approval granted
- Proposed Onshore Exploratory drilling of 6 nos. of wells in OALP-V Block… — environmental approval granted
4 Oil India (OIL) projects in Bikaner