Quick answers
What is this project?
Ramapura Silica Sand Mining Project of Ramapura Minerals Private Limited is situated near Village – Ramapura, Tehsil & District - Karauli, Rajasthan and is for expansion of Ramapura Silica Sand Mine (M.L. No. 04/ 1994) for increase in production from 60,000 TPA (Silica Sand) to 2,82,360 TPA- Total Excavation (Mineral -2,25,890 TPA and Waste (Use as masonry stone) - 56,470 TPA) from an area of 18.12 Ha. (Sawaichak Gair Mumkin Pahar – Govt. Land - 10.3744 Ha. & Diverted Forest Land – 7.7456 Ha.) is a lapsed mining project in Rampura, Karauli, Rajasthan. The site covers 44.8 acres.
Who is building it?
The applicant is Ms Ramapuraminerals PVT LTD.
Has it been approved?
No. The application was lapsed on 1 Mar 2023, so it is no longer under consideration.
Where is it?
In Rampura, Karauli, Rajasthan.
How big is it?
It has a stated cost of ₹2.5 crore and a site of 44.8 acres.
When was it filed?
The application was filed on 1 Mar 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 1 Mar 2023 |
| Application filed | 1 Mar 2023 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Mining |
| Applicant | Ms Ramapuraminerals PVT LTD |
| Land area | 44.8 acres (18.1 ha) |
| Project cost | ₹2.5 crore |
| Village / locality | Rampura |
| Taluk / tehsil | Karauli |
| District | Karauli |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-02200 |
In context
252 applications in Karauli since January 2022 are in the same category (Mining): 67 approved, 48 filed or under review, and 137 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 44.8 acres, this one is larger than 95% of them.
No other mining lease on record is within 500 m of this site; 28 have applied within 5 km.
Where it is
Rampura, Karauli, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Earlier Granted EC from Shri Gopal Lal Agarwal S/o Shri Prabhu Lal… — lapsed, 850 m away
- Shri Puspendra Kumar Agarwal [re Appraisal of Ec Granted From Deiaa Karauli to… — returned to applicant, 850 m away
- Expansion in Production Capacity of Silica Sand & inclusion of masonry stone… — more information requested, 1000 m away
- EC Re-appraisal of Existing Silica Sand Mining Lease (M.L. No. – 09/2003,… — environmental approval granted, 1000 m away
- Smt. Pushpa (ML No. - 18/2002) — lapsed, 1.1 km away
- Shri Sunil Garg, M.L.No. 03/2002 — lapsed, 1.2 km away
- Shri Sunil Garg, M.L.No. 03/2002 — returned to applicant, 1.2 km away
- Re-appraisal of Environment Clearance granted by DEIAA to SEIAA in compliance… — lapsed, 1.3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.