What is "Limestone Mining Project, ML No.- 105/1996",?
"Limestone Mining Project, ML No.- 105/1996" is an approved mining project in Sinla, Jaitaran, Pali, Rajasthan. The site covers 9.3 acres.
Who is building it?
The applicant is Anop Kanwar.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 3 May 2024), as of 27 Nov 2026.
Where is it?
In Sinla, Jaitaran, Pali, Rajasthan.
How big is it?
It has a stated cost of ₹28 lakh and a site of 9.3 acres.
When was it filed?
The application was filed on 16 Feb 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 3 May 2024 |
| Application filed | 16 Feb 2024 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Mining |
| Applicant | Anop Kanwar |
| Land area | 9.3 acres (3.8 ha) |
| Project cost | ₹28 lakh |
| Village / locality | Sinla |
| Taluk / tehsil | Jaitaran |
| District | Pali |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-04019 |
In context
1,118 applications in Pali since January 2022 are in the same category (Mining): 623 approved, 93 filed or under review, and 402 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 9.3 acres, this one is larger than 71% of them.
No other mining lease on record is within 500 m of this site; 42 have applied within 5 km.
Where it is
Sinla, Jaitaran, Pali, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environmental Clearance (from M/s Shree Karni Minerals to M/s Maa… — under environmental review, 0 m away
- Re-appraisal of Environmental Clearance granted by DEIAA, Pali(Raj.) of our… — environmental approval granted, 0 m away
- Transfer of Mine EC from M/s. Siddhi Vinayak Cement Limited to M/s. Nuvoco… — lapsed, 800 m away
- Re-appraisal of Environmental Clearance granted by DEIAA, Pali(Raj.) of our… — environmental approval granted, 1.3 km away
- Re-appraisal of Existing Sinla Limestone Mining Project, M.L. No- 81/94… — environmental approval granted, 1.4 km away
- Re-appraisal of Existing Sinla Limestone Mining Project, M.L. No- 383/91,… — environmental approval granted, 1.5 km away
- Re-Appraisal of Environmental Clearance Granted by Deiaa Pali (Rajasthan) of… — under environmental review, 1.8 km away
- Reappraisal of Existing Sinla Limestone mine, M.L. No- 19/95, Area- 4.99 ha… — environmental approval granted, 2 km away
More from Anop Kanwar in Pali
- Re-appraisal of Environmental Clearance granted by DEIAA, Pali(Raj.) of our… — environmental approval granted
- Re-appraisal of Environmental Clearance granted by DEIAA, Pali(Raj.) of our… — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.