Quick answers
What is this project?
Ekalsinga Granite & Masonary Stone Mine (M.L. NO.: 237A/2009), Lease Area- 1.00 Hects., Production Capacity- 190260 TPA (150205 Tones Granite + 40055 Tones Masonary Stone) of mineral Granite & Masonary Stone at Khasra No. 407, N/v- Ekalsinga, Tehsil- Kekri, District- Kekri, Rajasthan in favor of Mr. Khem Chand Lodha is a withdrawn mining project in Ekalsinga, Kekri, Ajmer, Rajasthan. The site covers 2.5 acres.
Who is building it?
The applicant is Khem Chand Lodha.
Has it been approved?
No. The application was withdrawn on 6 Jul 2026, so it is no longer under consideration.
Where is it?
In Ekalsinga, Kekri, Ajmer, Rajasthan.
How big is it?
It has a stated cost of ₹1.3 crore and a site of 2.5 acres.
When was it filed?
The application was filed on 19 May 2024.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Ekalsinga Granite & Masonary Stone Mine (M.L. NO.: 237A/2009), Lease Area- 1.00 Hects.,…
Project details
| Status | Withdrawn |
|---|---|
| Status since | 6 Jul 2026 |
| Application filed | 19 May 2024 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Mining |
| Applicant | Khem Chand Lodha |
| Land area | 2.5 acres (1 ha) |
| Project cost | ₹1.3 crore |
| Village / locality | Ekalsinga |
| Taluk / tehsil | Kekri |
| District | Ajmer |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-07599 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Ownership transfer filed 19 May 2024 (this page) | Withdrawn | 2.5 acres | ₹1.3 crore |
| New project filed 8 May 2024 | Returned to applicant | 2.5 acres | ₹1.3 crore |
In context
1,559 applications in Ajmer since January 2022 are in the same category (Mining): 904 approved, 102 filed or under review, and 553 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 2.5 acres, this one is smaller than 96% of them.
10 other mining leases have applied within 500 m of this site; together with this one they cover 31.6 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 52 mining leases have applied within 5 km.
Where it is
Ekalsinga, Kekri, Ajmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Ekalsinga Granite & Masonary Stone Mine, M.L. No. 237/2009", Khasra No.: 407 — environmental approval granted, 0 m away
- Ekalsinga Granite & Masonary Stone Mine, M.L. No. 237/2009", Khasra No.: 407 — environmental approval granted, 0 m away
- Re-appraisal of EC issued by DEIAA for Ekalsinga Granite & Masonary Stone Mine… — withdrawn, 0 m away
- Ekalsinga Granite & Masonary Stone Mine (M.L. NO.: 237A/2009), Lease Area-… — returned to applicant, 0 m away
- Re-appraisal of EC issued by DEIAA for Ekalsinga Granite & Masonary Stone Mine… — returned to applicant, 0 m away
- EC Re-appraisal of Existing Granite Mining Lease (M.L. No. – 15/2018, Area:… — environmental approval granted, 100 m away
- Re-appraisal of EC issued by DEIAA to Ekalsinga Granite Mine (M.L. No.:… — environmental approval granted, 100 m away
- M/s Shri Shiv Mines & Minerals, Masonary Stone & Granite Mining , M.L No-… — environmental approval granted, 100 m away
More from Khem Chand Lodha in Ajmer
- M/s Mateshwari Minerals, Quartz & Feldspar Mine, ML No.208/2008 — lapsed
- Balapura Quartz & Feldspar Mine (M.L. NO.: 209/2008) — environmental approval granted
- Ekalsinga Granite & Masonary Stone Mine, M.L. No. 237/2009", Khasra No.: 407 — environmental approval granted
- Ekalsinga Granite & Masonary Stone Mine, M.L. No. 237/2009", Khasra No.: 407 — environmental approval granted
- Re-appraisal of EC issued by DEIAA for Nizampura Quartz & Feldspar Mine, M.L.… — environmental approval granted
- Re-appraisal of EC issued by DEIAA for Ekalsinga Granite & Masonary Stone Mine… — returned to applicant
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.