Re-Appraisal of Environmental Clearance Granted by Deiaa Jalore(Rajasthan) of Our Existing Granite Mining Project M.L.No.27/1996 Area 1.00 Hect. N/V Bala Tehsil Ahore District Jalore(Raj.) in Favour of Kalki Devi.

Re-Appraisal of Environmental Clearance Granted by Deiaa Jalore(Rajasthan) of Our Existing Granite Mining Project M.L.No.27/1996 Area 1.00 Hect. N/V Bala Tehsil Ahore District Jalore(Raj.) in Favour of Kalki Devi is a lapsed mining project in Mailawas, Siwana, Barmer, Rajasthan. The site covers 2.5 acres. Its stated project cost is ₹80 lakh. As of 27 Nov 2026, its status is “Lapsed” (since 26 Apr 2025).

See it on the live map All projects in Barmer

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Re-Appraisal of Environmental Clearance Granted by Deiaa Jalore(Rajasthan) of Our Existing Granite Mining Project M.L.No.27/1996 Area 1.00 Hect. N/V Bala Tehsil Ahore District Jalore(Raj.) in Favour of Kalki Devi is a lapsed mining project in Mailawas, Siwana, Barmer, Rajasthan. The site covers 2.5 acres.

Who is building it?

The applicant is Kalki Devi.

Has it been approved?

No. The application was lapsed on 26 Apr 2025, so it is no longer under consideration.

Where is it?

In Mailawas, Siwana, Barmer, Rajasthan.

How big is it?

It has a stated cost of ₹80 lakh and a site of 2.5 acres.

When was it filed?

The application was filed on 7 Nov 2024.

Project details

StatusLapsed
Status since26 Apr 2025
Application filed7 Nov 2024
Approval soughtEnvironmental approval
Application typeNew project
SectorMining
ApplicantKalki Devi
Land area2.5 acres (1 ha)
Project cost₹80 lakh
Village / localityMailawas
Taluk / tehsilSiwana
DistrictBarmer
StateRajasthan
Location fromSite boundary on record
Our referenceWID-RJ-11203

In context

878 applications in Barmer since January 2022 are in the same category (Mining): 465 approved, 100 filed or under review, and 313 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 2.5 acres, this one is smaller than 97% of them.

No other mining lease on record is within 500 m of this site; 9 have applied within 5 km.

Where it is

Mailawas, Siwana, Barmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.