Quick answers
What is this project?
Existing Masonary Stone (Minor Mineral) Mining Project, M.L. No.- 161/2006, Area– 1.00 Ha. Near village Samer , Tehsil. Datanram Garh District . Sikar ( Rajasthan).In Favour Of Sh. SukhLal Babariya is a lapsed mining project in Samer, Danta Ramgarh, Sikar, Rajasthan. The site covers 2.5 acres.
Who is building it?
The applicant is Sukh Babariya.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Samer, Danta Ramgarh, Sikar, Rajasthan.
How big is it?
It has a stated cost of ₹45 lakh and a site of 2.5 acres.
When was it filed?
The application was filed on 16 Jan 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 16 Jan 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Sukh Babariya |
| Land area | 2.5 acres (1 ha) |
| Project cost | ₹45 lakh |
| Village / locality | Samer |
| Taluk / tehsil | Danta Ramgarh |
| District | Sikar |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-12105 |
In context
837 applications in Sikar since January 2022 are in the same category (Mining): 470 approved, 62 filed or under review, and 305 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 2.5 acres, this one is smaller than 99% of them.
7 other mining leases have applied within 500 m of this site; together with this one they cover 19.8 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 52 mining leases have applied within 5 km.
Where it is
Samer, Danta Ramgarh, Sikar, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Re-appraisal of EC granted by DEIAA to SEIAA in compliance of MoEF&CC O.M.… — environmental approval granted, 0 m away
- Transfer of Environment Clearance [From Suresh Kumar Sharma To Sh. Sukhlal… — environmental approval granted, 0 m away
- "Reappraisal of EC from DEIAA to SEIAA" Existing Masonry Stone Mining Project… — lapsed, 50 m away
- "Reappraisal of EC from DEIAA to SEIAA"Existing Masonry Stone Mining Project,… — lapsed, 50 m away
- "Reappraisal of EC from DEIAA to SEIAA"Existing Masonry Stone Mining Project,… — lapsed, 100 m away
- "Reappraisal of EC from DEIAA to SEIAA" Existing Masonry stone Mining Project,… — environmental approval granted, 200 m away
- Existing Masonary Stone (Minor Mineral) Mining Project, M.L. No.- 331/2006,… — lapsed, 250 m away
- Re-appraisal of Environmental Clearance granted by DEIAA, Sikar of our… — environmental approval granted, 250 m away
More from Sukh Babariya in Sikar
- Re-appraisal of EC granted by DEIAA to SEIAA in compliance of MoEF&CC O.M.… — environmental approval granted
- Transfer of Environment Clearance [From Suresh Kumar Sharma To Sh. Sukhlal… — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.