Quick answers
What is this project?
Re-appraisal of EC issued by DEIAA for Suhawa Quartz & Feldspar Mine (M.L. NO.: 210/2005), Lease Area- 4.969Hects., at Khasra No. 253,254/1,263,440,441,443 N/v- Suhawa, Tehsil- Beawar, District- Beawar, Rajasthan in favor of Mr. Shankhar Singh S/o Bahadur Mehrat is an approved mining project in Suhawa, Beawar, Ajmer, Rajasthan. The site covers 12.3 acres.
Who is building it?
The applicant is Shankar.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 25 Dec 2024), as of 27 Nov 2026.
Where is it?
In Suhawa, Beawar, Ajmer, Rajasthan.
How big is it?
It has a stated cost of ₹1 crore and a site of 12.3 acres.
When was it filed?
The application was filed on 25 Aug 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 25 Dec 2024 |
| Application filed | 25 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Shankar |
| Land area | 12.3 acres (5 ha) |
| Project cost | ₹1 crore |
| Village / locality | Suhawa |
| Taluk / tehsil | Beawar |
| District | Ajmer |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-14106 |
In context
1,559 applications in Ajmer since January 2022 are in the same category (Mining): 904 approved, 102 filed or under review, and 553 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 12.3 acres, this one is larger than 91% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 22.8 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 44 mining leases have applied within 5 km.
Where it is
Suhawa, Beawar, Ajmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Reappraisal of the EC granted by DEIAA Ajmer for Quartz and Feldspar Mining… — environmental approval granted, 450 m away
- Re-appraisal of earlier granted EC by DEIAA Ajmer (Raj.)vide latter no.… — lapsed, 2 km away
- Re-appraisal of earlier granted EC by DEIAA Ajmer (Raj.)vide latter no.… — environmental approval granted, 2 km away
- "Reappraisal of the EC granted by DEIAA Ajmer for Quartz and Feldspar Mining… — lapsed, 2.1 km away
- Ratanpura Quartz & feldspar mine,ML NO. - 222/2008, Area-4.0 Hact., N.V-… — lapsed, 2.1 km away
- "Reappraisal of the EC granted by DEIAA Ajmer for Quartz and Feldspar Mining… — environmental approval granted, 2.3 km away
- Reappraisal of the EC granted by DEIAA Ajmer for Quartz and Feldspar Mining… — environmental approval granted, 2.4 km away
- "Reappraisal of the EC granted by DEIAA Ajmer for Quartz & Feldspar Mining… — lapsed, 2.5 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.