What is this project?
Environmental clearance for Transfer of Environment Clearance [From Santosh Devi Jain To Shri Hanuman Singh Rathore S/O Shri Bhanwar Singh Rathore of Limestone Mining Project, ML. NO.-45/07, with Production Capacity 128325 TPA over an Area – 4.0 Hectare, Near Village-Basni Hari Singh, Tehsil-Bh opalgarh, District-Jodhpur (Rajasthan) ]by Applicant Shri Hanuman Singh Rathore S/O Shri Bhanwar Singh Rathore is a lapsed mining project in Basni Harisingh, Bhopalgarh, Jodhpur, Rajasthan. The site covers 9.9 acres.
Who is building it?
The applicant is Natmal Dadhich.
Has it been approved?
No. The application was lapsed on 15 Aug 2025, so it is no longer under consideration.
Where is it?
In Basni Harisingh, Bhopalgarh, Jodhpur, Rajasthan.
How big is it?
It has a stated cost of ₹50 lakh and a site of 9.9 acres.
When was it filed?
The application was filed on 10 Jan 2025.
Project details
| Status | Lapsed |
|---|---|
| Status since | 15 Aug 2025 |
| Application filed | 10 Jan 2025 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Mining |
| Applicant | Natmal Dadhich |
| Land area | 9.9 acres (4 ha) |
| Project cost | ₹50 lakh |
| Village / locality | Basni Harisingh |
| Taluk / tehsil | Bhopalgarh |
| District | Jodhpur |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-22127 |
In context
11,954 applications in Jodhpur since January 2022 are in the same category (Mining): 4,406 approved, 210 filed or under review, and 7,338 withdrawn, lapsed or rejected. The approved ones took a median of 7 months from filing to approval. At 9.9 acres, this one is larger than 98% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 19.8 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 1 mining lease has applied within 5 km.
Where it is
Basni Harisingh, Bhopalgarh, Jodhpur, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Re-appraisal of Environment Clearance granted by DEIAA to SEIAA in compliance… — environmental approval granted, 0 m away
- Re-appraisal of Environment Clearance granted by DEIAA to SEIAA in compliance… — lapsed, 0 m away
- Re-appraisal of Environment Clearance granted by DEIAA to SEIAA in compliance… — environmental approval granted, 200 m away
- Expansion in production capacity from 36,000 TPA [ROM] to 2,50,091 TPA [ROM]… — environmental approval granted, 7.6 km away
- Re-appraisal of Environmental Clearance granted by DEIAA, Jodhpur [Rajasthan]… — environmental approval granted, 7.6 km away
- Proposed Expansion in production capacity from 36,000 TPA [ROM] to 3,64,781… — more information requested, 7.6 km away
- Road and development of the existing Bhuriya Baba Temple — lapsed, 15.9 km away
- Widening From Two Lane to Four Lane With Paved Shoulder From Km 226+400 to Km… — lapsed, 18.8 km away
More from Natmal Dadhich in Jodhpur
- Re-appraisal of Environment Clearance granted by DEIAA to SEIAA in compliance… — environmental approval granted
- Re-appraisal of Environment Clearance granted by DEIAA to SEIAA in compliance… — environmental approval granted