Re-appraisal of earlier granted EC by DEIAA Ajmer (Raj.)vide latter no. DEIAA/AJM/M-Sectt/2016-17/100 dated 19/09/2016 with production capacity 60775 TPA of existing Kharwa Quartz & Feldspar Mining Project M.L. no- 141/04 Lease Area =4.52 Hect. Khasra No 2480, 2484, 3806, 3807, 3808, 2483 Near Village – Kharwa Tehsil-Masuda, Distt. Beawar (Raj.)

Re-appraisal of earlier granted EC by DEIAA Ajmer (Raj.)vide latter no. DEIAA/AJM/M-Sectt/2016-17/100 dated 19/09/2016 with production capacity 60775 TPA of existing Kharwa Quartz & Feldspar Mining Project M.L. no- 141/04 Lease Area =4.52 Hect. Khasra No 2480, 2484, 3806, 3807, 3808, 2483 Near Village – Kharwa Tehsil-Masuda, Distt. Beawar (Raj.) is a lapsed mining project in Kharwa, Masuda, Ajmer, Rajasthan. The site covers 11.2 acres. Its stated project cost is ₹50 lakh. As of 27 Nov 2026, its status is “Lapsed” (since 26 Aug 2025).

See it on the live map All projects in Ajmer

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Re-appraisal of earlier granted EC by DEIAA Ajmer (Raj.)vide latter no. DEIAA/AJM/M-Sectt/2016-17/100 dated 19/09/2016 with production capacity 60775 TPA of existing Kharwa Quartz & Feldspar Mining Project M.L. no- 141/04 Lease Area =4.52 Hect. Khasra No 2480, 2484, 3806, 3807, 3808, 2483 Near Village – Kharwa Tehsil-Masuda, Distt. Beawar (Raj.) is a lapsed mining project in Kharwa, Masuda, Ajmer, Rajasthan. The site covers 11.2 acres.

Who is building it?

The applicant is Bheru Lal Rao.

Has it been approved?

No. The application was lapsed on 26 Aug 2025, so it is no longer under consideration.

Where is it?

In Kharwa, Masuda, Ajmer, Rajasthan.

How big is it?

It has a stated cost of ₹50 lakh and a site of 11.2 acres.

When was it filed?

The application was filed on 13 Feb 2025.

Project details

Official titleProposal for Re-appraisal of earlier granted EC by DEIAA Ajmer (Raj.)vide latter no. DEIAA/AJM/M-Sectt/2016-17/100 dated 19/09/2016 with production capacity 60775 TPA of existing Kharwa Quartz & Feldspar Mining Project M.L. no- 141/04 Lease Area =4.52 Hect. Khasra No 2480, 2484, 3806, 3807, 3808, 2483 Near Village – Kharwa Tehsil-Masuda, Distt. Beawar (Raj.)
StatusLapsed
Status since26 Aug 2025
Application filed13 Feb 2025
Approval soughtEnvironmental approval
Application typeOwnership transfer
SectorMining
ApplicantBheru Lal Rao
Land area11.2 acres (4.5 ha)
Project cost₹50 lakh
Village / localityKharwa
Taluk / tehsilMasuda
DistrictAjmer
StateRajasthan
Location fromSite boundary on record
Our referenceWID-RJ-23739

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Ownership transfer filed 13 Feb 2025 (this page)Lapsed11.2 acres₹50 lakh
New project filed 11 Jul 2024Lapsed11.2 acres₹50 lakh

In context

1,559 applications in Ajmer since January 2022 are in the same category (Mining): 904 approved, 102 filed or under review, and 553 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 11.2 acres, this one is larger than 78% of them.

No other mining lease on record is within 500 m of this site; 27 have applied within 5 km.

Where it is

Kharwa, Masuda, Ajmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.