What is this project?
Sandstone Mineral Mining Project, Q.L. No.-106 with Production Capacity-1800 TPA (ROM) {Sealable Mineral- 1710 tonnes and Mineral Waste- 90 tonnes}, Area:- 0.18 ha. (Govt. Land) is a lapsed mining project in Keru, Jodhpur, Rajasthan. The site covers 0.4 acres.
Who is building it?
The applicant is MULA RAm.
Has it been approved?
No. The application was lapsed on 2 Feb 2026, so it is no longer under consideration.
Where is it?
In Keru, Jodhpur, Rajasthan.
How big is it?
It has a stated cost of ₹36 lakh and a site of 0.4 acres.
When was it filed?
The application was filed on 23 Sept 2025.
Project details
| Official title | Sandstone Mineral Mining Project, Q.L. No.-106 with Production Capacity-1800 TPA (ROM) {Sealable Mineral- 1710 tonnes and Mineral Waste- 90 tonnes}, Area:- 0.18 ha. (Govt. Land), at Near Village- Keru-A, Tehsil:- Jodhpur & District:- Jodhpur (Rajasthan) of applicant Shri Mula Ram S/o Shri Babu Lal. |
|---|---|
| Status | Lapsed |
| Status since | 2 Feb 2026 |
| Application filed | 23 Sept 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | MULA RAm |
| Land area | 1,800 m² |
| Project cost | ₹36 lakh |
| Village / locality | Keru |
| Taluk / tehsil | Jodhpur |
| District | Jodhpur |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-27590 |
In context
11,954 applications in Jodhpur since January 2022 are in the same category (Mining): 4,406 approved, 210 filed or under review, and 7,338 withdrawn, lapsed or rejected. The approved ones took a median of 7 months from filing to approval. At 0.4 acres, this one is smaller than 98% of them.
342 other mining leases have applied within 500 m of this site; together with this one they cover 152.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 3,105 mining leases have applied within 5 km.
Where it is
Keru, Jodhpur, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Existing (Non-Operational) Sandstone Mining Project; Q.L. No.-106, Area:… — environmental approval granted, 0 m away
- Ranveer Singh Gehlot S/O Babu Lala Gehlot Ql.No. 119 Keru-A — environmental approval granted, 50 m away
- 95, Keru-A — lapsed, 50 m away
- Sanjay Purohit,ql-93,keru-A — lapsed, 50 m away
- Transfer of Environment Clearance From Name Chandra Singh S/O Banshi Lal to… — lapsed, 50 m away
- Kamla Kanwar W/O Jabar Singh Ql. No. 117 Keru-A — environmental approval granted, 100 m away
- 116 a Keru a — more information requested, 100 m away
- Digambar Singh S/O Jabar Singh Ql No 91 Keru-A — environmental approval granted, 100 m away
More from MULA RAm in Jodhpur
- Existing (Non-Operational) Sandstone Mining Project; Q.L. No.-106, Area:… — environmental approval granted
- SH. Mula Ram S/O Baga Ram Ql.No. 647 Pabumagra — environmental approval granted
- Mula Ram S/O Puna Ram Ql.No. 500 Keru — environmental approval granted
- SH. Mula Ram S/O Puna Ram Ql.No. 501 N/V Keru — environmental approval granted
- SH. Moolaram Parihar S/O SH. Gokul Ram Ql No. 1149,keru — lapsed
- SH. Mula Ram S/O SH. Puna Ram,ql-1161,keru — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.