| Official title | Proposed Manufacturing of Cement (Clinker Grinding Unit) along with the existing slag grinding unit at Plot No. E 33(A) & E-34(A) RIICO Industrial Area, Behror, District- Alwar Rajasthan by M/S Shree Dayal Minerals |
|---|---|
| Status | Cleared for impact study |
| Status since | 10 Jun 2025 |
| Application filed | 23 May 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Shree Dayal Minerals |
| Land area | 3,000 m² |
| Project cost | ₹3.7 crore |
| Village / locality | Bahror |
| Taluk / tehsil | Behror |
| District | Alwar |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-28375 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 13 Apr 2026 | Environmental approval granted | 0.7 acres | ₹3.7 crore |
| Early planning filed 23 May 2025 (this page) | Cleared for impact study | 0.7 acres | ₹3.7 crore |
In context
127 applications in Alwar since January 2022 are in the same category (Industry): 93 approved, 18 filed or under review, and 16 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 0.7 acres, this one is smaller than 75% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bahror, Behror, Alwar, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Manufacturing of Cement (Clinker Grinding Unit) by M/S Shree Dayal… — environmental approval granted, 0 m away
- Proposed Expansion for Manufacturing of Cement (Clinker Grinding Unit) — not approved, 200 m away
- Proposed Clinker Grinding Unit of 180 TPD capacity 59,400 TPA… — environmental approval granted, 250 m away
- Proposed Standalone Clinker Grinding Unit - 180 Tpd (59,400 Tpa) — withdrawn, 300 m away
- Proposed Standalone Clinker Grinding Unit - 180 Tpd (59,400 Tpa) — cleared for impact study, 300 m away
- EC Amendment in Expansion of Grain based Distillery (140 KLPD To 160 KLPD) by… — environmental approval granted, 6.1 km away
- EXPANSION IN EXISTING Bulk Drugs & Drug Intermediates Manufacturing Unit — environmental approval granted, 7.9 km away
- EXPANSION IN EXISTING Bulk Drugs & Drug Intermediates Manufacturing Unit — returned to applicant, 7.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.