Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 12 Aug 2026 |
| Application filed | 2 Jun 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Jprpark Infra LLP |
| Use | Residential |
| Units | 588 |
| Floors (tallest) | 18 |
| Basements | 1 |
| Height | 56 m |
| Parking spaces | 471 |
| Land area | 2.4 acres (1 ha) |
| Built-up area | 65,357 m² (7,03,496 sq ft) |
| Plot area | 9,923 m² (1,06,810 sq ft) |
| Project cost | ₹197 crore |
| Village / locality | Jaipur Nagar Nigam Area |
| Taluk / tehsil | Jaipur |
| District | Jaipur |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-34102 |
What the filings say
What is planned
The applicant, JPR Park Infra LLP, proposes to develop "V Park," a group housing project under the Chief Minister Jan Awas Yojana (Provision 3A). The project is planned for a plot of 9,923.29 square metres (2.45 acres) in Jaipur, Rajasthan.
The development consists of a single building block with a basement, stilt, ground floor, and 18 upper floors (B+S+G+18). The total gross built-up area is 65,357.27 square metres. The project will provide 588 residential units, categorized as follows:
- LIG (Low Income Group): 462 units
- EWS (Economically Weaker Section): 126 units
Amenities include a club house (1,550.92 square metres), a swimming pool, and commercial space of 492.93 square metres. The building's terrace height is 56 metres, reaching 63 metres at the machine room level.
Layout and design
The site layout allocates 2,753.66 square metres (27.75%) for ground coverage. A significant portion of the plot, 5,804.72 square metres (58.50%), is designated as open area. The landscape area covers 1,987.34 square metres (20.03%), which includes 1,164.91 square metres of softscape on land and 822.43 square metres of hardscape on the podium.
Parking is planned for 471 Equivalent Car Spaces (ECU), exceeding the requirement of 361 ECU. This includes provisions for 118 cars and 1,059 scooters, distributed across the basement, stilt, and open surface areas. Ten percent of the required parking (36 ECU) will be reserved for electric vehicle (EV) charging.
Water, power and access
During the operational phase, the total water requirement is estimated at 366 kilolitres per day (KLD). This comprises 268 KLD of fresh water, to be sourced from the Public Health Engineering Department (PHED) or groundwater, and 98 KLD of recycled water.
A sewage treatment plant (STP) with a capacity of 358 KLD will be installed using Moving Bed Biofilm Reactor (MBBR) technology. Treated water will be reused for flushing (85.5 KLD), landscaping (8.5 KLD), and general washing. Excess treated water (174 KLD) is intended for nearby farmers, construction activities, or discharge into the sewer line.
Power will be supplied by Jaipur Vidyut Vitran Nigam Limited. The connected load is 4,678.70 KW, with a maximum demand of 2,344.00 KW. For backup, two diesel generator (DG) sets of 200 kVA each are proposed. Energy conservation measures include solar PV panels with a capacity of 55.16 KW and the use of solar lighting for landscape areas.
Environmental safeguards
Solid waste generation is estimated at 1,461 kg per day. The applicant proposes an on-site mechanical composting system (The Smart Composter) with a capacity of 997 kg per day to treat biodegradable waste. Non-biodegradable waste will be sent to municipal disposal sites.
For rainwater management, seven recharge structures with a capacity of 24.74 cubic metres each are planned. Additionally, three storage tanks with a total capacity of 223.2 cubic metres will be constructed to store harvested water for landscaping.
The plantation plan includes 248 native trees, such as Ashok (103), Shisham (36), Amaltas (36), and Neem (34).
Timeline
The applicant's project report outlines a five-phase implementation schedule over 24 months:
- Phase I (0–4 Months): Planning and permissions
- Phase II (4–8 Months): Design and procurement
- Phase III (8–12 Months): Execution
- Phase IV (12–18 Months): Commissioning and awareness
- Phase V (18–24 Months): Monitoring and evaluation
V Park site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
284 applications in Jaipur since January 2022 are in the same category (Buildings & townships): 196 approved, 45 filed or under review, and 42 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 2.4 acres, this one is smaller than 57% of them.
11 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jaipur Nagar Nigam Area, Jaipur, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Kedia Panchtatva — under environmental review, 1.2 km away
- Proposed Residential Apartments "Star Islands" at Khasra No. 1046, 1739 &… — environmental approval granted, 3.4 km away
- PROPOSED FOREST LAND FOR DIVERSION OF 0.70 Ha. "CONSTRUCTION OF BUS STAND " — more information requested, 3.7 km away
- Proposed Forest Land for Diversion for "construction of Road "on Topo Sheet… — lapsed, 3.7 km away
- Approach Access for Sandford High School at Sirsi Link Road, Near Govt.… — lapsed, 3.7 km away
- Group Housing Project "AAHVAN" at Plot No. G-8 and Khasra No. 938, 939, 940 &… — environmental approval granted, 3.9 km away
- Group Housing Project "AAHVAN" at Plot No. G-8 and Khasra No. 938, 939, 940 &… — lapsed, 3.9 km away
- Anant Kailash — lapsed, 4.4 km away