What is Developing? Open the mapMap

LapsedMining · Ajmer, Rajasthan

Re-appraisal of Environmental Clearance granted by DEIAA, Ajmer [Rajasthan] of our Existing Quartz & Feldspar Mining Project; M.L. No.-53/2008, Area: 4.0001 Hect

Re-appraisal of Environmental Clearance granted by DEIAA, Ajmer [Rajasthan] of our Existing Quartz & Feldspar Mining Project; M.L. No.-53/2008, Area: 4.0001 Hect is a lapsed mining project in Tilana, Nasirabad, Ajmer, Rajasthan. The site covers 9.9 acres. Its stated project cost is ₹1 crore. As of 27 Nov 2026, its status is “Lapsed” (since 10 Jul 2026).

See it on the live map All projects in Ajmer

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Re-appraisal of Environmental Clearance granted by DEIAA, Ajmer [Rajasthan] of our Existing Quartz & Feldspar Mining Project; M.L. No.-53/2008, Area: 4.0001 Hect is a lapsed mining project in Tilana, Nasirabad, Ajmer, Rajasthan. The site covers 9.9 acres.

Who is building it?

The applicant is Sumit Maheshwari.

Has it been approved?

No. The application was lapsed on 10 Jul 2026, so it is no longer under consideration.

Where is it?

In Tilana, Nasirabad, Ajmer, Rajasthan.

How big is it?

It has a stated cost of ₹1 crore and a site of 9.9 acres.

When was it filed?

The application was filed on 9 Jun 2026.

Project details

Official titleRe-appraisal of Environmental Clearance granted by DEIAA, Ajmer [Rajasthan] of our Existing Quartz & Feldspar Mining Project; M.L. No.-53/2008, Area: 4.0001 Hect., at Near Village:- Tilana, Tehsil:- Nasirabad, District:- Ajmer (Raj.) in favor of Shri Sumit Maheshwari.
StatusLapsed
Status since10 Jul 2026
Application filed9 Jun 2026
Approval soughtEnvironmental approval
Application typeNew project
SectorMining
ApplicantSumit Maheshwari
Land area9.9 acres (4 ha)
Project cost₹1 crore
Village / localityTilana
Taluk / tehsilNasirabad
DistrictAjmer
StateRajasthan
Location fromSite boundary on record
Our referenceWID-RJ-35640

In context

1,559 applications in Ajmer since January 2022 are in the same category (Mining): 904 approved, 102 filed or under review, and 553 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 9.9 acres, this one is larger than 60% of them.

No other mining lease on record is within 500 m of this site; 61 have applied within 5 km.

Where it is

Tilana, Nasirabad, Ajmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.