Quick answers
What is this project?
"Construction of 132 kV S/C Kanwat-Sanwalpura line at 220 kV GSS Kanwat, District-Sikar (Rajasthan)" is a proposed power project in Balajinagar, Khendela, Sikar, Rajasthan. The site covers 484.5 acres.
Who is building it?
The applicant is Rajasthan Rajya Vidyut Prasaran Nigam Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Balajinagar, Khendela, Sikar, Rajasthan.
How big is it?
It has a stated cost of ₹9.6 crore; a site of 484.5 acres and 5.3 acres (2.1 ha) of forest land.
When was it filed?
The application was filed on 31 Jul 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 29 Oct 2026 |
| Application filed | 31 Jul 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Rajasthan Rajya Vidyut Prasaran Nigam Limited |
| Land area | 484.5 acres (196.1 ha) |
| Forest land | 5.3 acres (2.1 ha) |
| Project cost | ₹9.6 crore |
| Village / locality | Balajinagar |
| Taluk / tehsil | Khendela |
| District | Sikar |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-35722 |
In context
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Balajinagar, Khendela, Sikar, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Shri Vinod Kumar saini M.L.No. 320/2006 — environmental approval granted, 5 km away
- Shri Vinod Kumar saini M.L.No. 320/2006 — lapsed, 5 km away
- Reappraisal of Earlier Granted EC By DEIAA, Sikar (Raj.) Vide Letter No.… — environmental approval granted, 5 km away
- Reappraisal of Earlier Granted EC By DEIAA, Sikar (Raj.) Vide Letter No. F(… — lapsed, 5.2 km away
- "CONSTRUCTION OF APPROACH ROAD TO BALAJI TEMPLE "at VILLAGE-PITHAMPURI,SIKAR — more information requested, 6.7 km away
- Proposed Expansion in Production capacity from 3,070 TPA to 3,08,880 TPA (ROM)… — more information requested, 6.8 km away
- Transfer of Environmental Clearance (from Shri Praveen Gupta S/o Shri Rakesh… — lapsed, 6.8 km away
- Transfer of Environmental Clearance (from Shri Praveen Gupta S/o Shri Rakesh… — withdrawn, 6.8 km away
All 29 Rajasthan Rajya Vidyut Prasaran Nigam projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.