Quick answers
What is this project?
132 kV S/C Satyaya Fanta-Bhadla Transmission Line from 220 KV GSS Bhadla to 132 KV GSS Satyaya, District-Jaisalmer (Rajasthan) is a lapsed power project in Bhadriya, Pokaran, Jaisalmer, Rajasthan. The site covers 411.4 acres.
Who is building it?
The applicant is Rajasthan Rajya Vidyut Prasaran Nigam Limited.
Has it been approved?
No. The application was lapsed on 30 Jul 2026, so it is no longer under consideration.
Where is it?
In Bhadriya, Pokaran, Jaisalmer, Rajasthan.
How big is it?
It has a stated cost of ₹14.6 crore; a site of 411.4 acres and 1.5 acres (0.6 ha) of forest land.
When was it filed?
The application was filed on 5 May 2026.
Project details
| Official title | Construction of 132 kV S/C Satyaya Fanta-Bhadla Transmission Line from 220 KV GSS Bhadla to 132 KV GSS Satyaya, District-Jaisalmer (Rajasthan) |
|---|---|
| Status | Lapsed |
| Status since | 30 Jul 2026 |
| Application filed | 5 May 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Rajasthan Rajya Vidyut Prasaran Nigam Limited |
| Land area | 411.4 acres (166.5 ha) |
| Forest land | 1.5 acres (0.6 ha) |
| Project cost | ₹14.6 crore |
| Village / locality | Bhadriya |
| Taluk / tehsil | Pokaran |
| District | Jaisalmer |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-35922 |
In context
13 applications in Jaisalmer since January 2022 are in the same category (Power): 0 approved, 11 filed or under review, and 1 withdrawn, lapsed or rejected. At 411.4 acres, this one is larger than 67% of them.
Where it is
Bhadriya, Pokaran, Jaisalmer, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Permission for Underground Ofc Laying Work Along Pwd Road Nachna Phata -1190… — lapsed, 13.7 km away
- Re-Appraisal of Environmental Clearance Granted by Deiaa Jaisalmer (Rajasthan)… — lapsed, 30.2 km away
- Gypsum Mining — application filed, 35.6 km away
- Full title of the Project: "Construction of Approach Access for Proposed… — forest land use approved, 52.3 km away
- Laying of Underground Optical Fiber Cable Along the Road Within Row from… — more information requested, 54.2 km away
- Approach Access for Proposed Bharat Petroleum Corporation Limited Retail… — forest land use approved, 55.4 km away
- Existing Gypsum (Minor Mineral) Mining Project, M.L. No. 07/03, Gypsum… — environmental approval granted, 56.6 km away
- EC transfer for exiting mining project Dolomite (Clay) Mine ML No… — lapsed, 56.7 km away
More from Rajasthan Rajya Vidyut Prasaran Nigam Limited in Jaisalmer
- 132 kV S/C Sangarh-Dangari Transmission Line for132 kV GSS Dangari,… — more information requested
- Underground 132KV , 400 Sq.mm S/c XLPE Cable system (3-Phase + 1 - Spare) of 5… — forest land use approved
3 Rajasthan Rajya Vidyut Prasaran Nigam projects in Jaisalmer
All 29 Rajasthan Rajya Vidyut Prasaran Nigam projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.