"Construction of Underground 132KV S/C Transmission Line using 132 KV 400 sq. mm XLPE Cable system (3-Phase + 1 - Spare) of 1.15 Km Route Length between 132 KV GSS Rajiasar and Proposed Railway TSS at Rajiyasar, District - Ganganagar (Rajasthan)" is an approved railway project in Rajiyasar, Suratgarh, Ganganagar, Rajasthan. The site covers 18.9 acres.
Who is building it?
The applicant is Rajasthan Rajya Vidyut Prasaran Nigam Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 22 Apr 2026), as of 27 Nov 2026.
Where is it?
In Rajiyasar, Suratgarh, Ganganagar, Rajasthan.
How big is it?
It has a stated cost of ₹6.4 crore; a site of 18.9 acres and 50 m² of forest land.
When was it filed?
The application was filed on 14 Jul 2023.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 22 Apr 2026 |
| Application filed | 14 Jul 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Railways & metro |
| Applicant | Rajasthan Rajya Vidyut Prasaran Nigam Limited |
| Land area | 18.9 acres (7.6 ha) |
| Forest land | 50 m² |
| Project cost | ₹6.4 crore |
| Village / locality | Rajiyasar |
| Taluk / tehsil | Suratgarh |
| District | Ganganagar |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-36097 |
Where it is
Rajiyasar, Suratgarh, Ganganagar, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Construction of Approach Access for U/G Tank of 50KL HSD Class-B of Consumber… — forest land use approved, 10 km away
- Approach Road for Proposed Hindustan Petroleum Corporation Ltd. Retail Outlet… — forest land use approved, 10.1 km away
- Expansion of Grain based distillery from 180 KLPD to 2000 KLPD & Co-generation… — withdrawn, 10.8 km away
- Proposed 180 KLD Grain based Distillery — environmental approval granted, 10.9 km away
- Proposed 180 KLD Grain based Distillery — environmental approval granted, 10.9 km away
- Proposed 180 KLD Grain based Distillery — cleared for impact study, 10.9 km away
- Expansion of Grain based distillery from 180 KLPD to 1200 KLPD & Co-generation… — under environmental review, 10.9 km away
- Proposed Clinker Grinding Unit with Cement Production Capacity of 6.0 Million… — environmental approval granted, 11.6 km away
More from Rajasthan Rajya Vidyut Prasaran Nigam Limited in Ganganagar
- Construction for LILO of 132kV S/C Srivijaynagar-Anoopgarh Transmission Line… — more information requested
All 29 Rajasthan Rajya Vidyut Prasaran Nigam projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.