What is Sri Ramilla Bapu?
Sri Ramilla Bapu is an approved mining project in Paidipalli, Velgatur, Jagitial, Telangana. The site covers 4.8 acres.
Who is building it?
The applicant is Ramilla Bapu.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 14 Jul 2023), as of 27 Nov 2026.
Where is it?
In Paidipalli, Velgatur, Jagitial, Telangana.
How big is it?
It has a stated cost of ₹20 lakh and a site of 4.8 acres.
When was it filed?
The application was filed on 14 Jul 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 14 Jul 2023 |
| Application filed | 14 Jul 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Ramilla Bapu |
| Land area | 4.8 acres (2 ha) |
| Project cost | ₹20 lakh |
| Village / locality | Paidipalli |
| Taluk / tehsil | Velgatur |
| District | Jagitial |
| State | Telangana |
| Location from | Site boundary on record |
| Our reference | WID-TG-01002 |
In context
69 applications in Jagitial since January 2022 are in the same category (Mining): 51 approved, 7 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 4.8 acres, this one is smaller than 65% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 6.3 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 11 mining leases have applied within 5 km.
Where it is
Paidipalli, Velgatur, Jagitial, Telangana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sri Kokkirala Venugopal Rao — more information requested, 300 m away
- Sri Kokkirala Venugopal Rao — environmental approval granted, 300 m away
- Mining project by M/s SAI SRINIVASA LAXMI STONE CRUSHER — environmental approval granted, 900 m away
- Mining project by M/s Sai Srinivasa Laxmi Stone Crusher — environmental approval granted, 950 m away
- Mining project by M/s Sai Srinivasa Laxmi Stone Crusher — not approved, 950 m away
- Mining project by M/s SAI SRINIVASA LAXMI STONE CRUSHER — environmental approval granted, 950 m away
- Mining project by M/s. Sai Srinivasa Laxmi Stone Crusher — environmental approval granted, 1.1 km away
- Mining project by M/s SATYANARAYANA SWAMY STONE CRUSHER — withdrawn, 1.1 km away
More from Ramilla Bapu in Jagitial
- Sri Kokkirala Venugopal Rao — more information requested
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.