Quick answers
What is this project?
Data Center Construction Project by M/s Amazon Data Services India Private Limited at at Survey No.147, Peddavedu Village, Shabad Mandal, Ranga Reddy District, Telangana State is an approved building project in Hayatabad, Shabad, Ranga Reddy, Telangana. It plans 3 towers on 96.6 acres.
Who is building it?
The applicant is Amazon Data Services India Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 3 Feb 2026), as of 27 Nov 2026.
Where is it?
In Hayatabad, Shabad, Ranga Reddy, Telangana.
How big is it?
It has a stated cost of ₹7,032.6 crore and a site of 96.6 acres.
When was it filed?
The application was filed on 18 Dec 2025.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 3 Feb 2026 |
| Application filed | 18 Dec 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Amazon Data Services India Private Limited |
| Use | Other |
| Towers | 3 |
| Land area | 96.6 acres (39.1 ha) |
| Built-up area | 1,08,087 m² (11,63,438 sq ft) |
| Plot area | 3,91,129 m² (42,10,073 sq ft) |
| Project cost | ₹7,032.6 crore |
| Village / locality | Hayatabad |
| Taluk / tehsil | Shabad |
| District | Ranga Reddy |
| State | Telangana |
| Location from | Site area on record |
| Our reference | WID-TG-02324 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 3 Aug 2026 | More information requested | 96.6 acres | ₹7,032.6 crore |
| New project filed 18 Dec 2025 (this page) | Environmental approval granted | 96.6 acres | ₹7,032.6 crore |
In context
882 applications in Ranga Reddy since January 2022 are in the same category (Buildings & townships): 667 approved, 107 filed or under review, and 108 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 96.6 acres, this one is larger than 97% of them.
20 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Hayatabad, Shabad, Ranga Reddy, Telangana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Data Center Construction Project by M/s Amazon Data Services India Private… — more information requested, 0 m away
- Data Center Construction Project by M/s Amazon Data Services India Private… — environmental approval granted, 850 m away
- Data Center Construction Project by M/s Amazon Data Services India Private… — environmental approval granted, 850 m away
- Proposed Data Center complex by CTRL S DATACENTERS LIMITED — environmental approval granted, 1.3 km away
- Proposed Data Center complex by CTRL S DATACENTERS LIMITED — cleared for impact study, 1.3 km away
- Industrial project by M/s Welspun Living Limited — environmental approval granted, 1.8 km away
- Industrial project by M/s. Welspun Living Limited (Formerly Welspun Flooring… — initial checks, 1.8 km away
- Industrial project by M/s Welspun Living Limited — environmental approval granted, 1.8 km away
More from Amazon Data Services India Private Limited in Ranga Reddy
- Data Center Construction Project by M/s Amazon Data Services India Private… — environmental approval granted
- Data Center Construction Project by M/s. Amazon Data Services India Private… — environmental approval granted
- Data Center Construction Project by M/s Amazon Data Services India Private… — environmental approval granted
- Data Center Construction Project by M/s Amazon Data Services India Private… — environmental approval granted
- Data Center Construction Project by M/s. Amazon Data Services India Private… — environmental approval granted
- Data Center Construction Project by M/s Amazon Data Services India Private… — environmental approval granted
9 Amazon Data Services projects in Hyderabad
All 16 Amazon Data Services projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.