Quick answers
What is Proposed Residential complex project - Kurra Srinivas Rao?
Proposed Residential complex project - Kurra Srinivas Rao is a proposed building project in Serilingampalli, Serilingampally, Ranga Reddy, Telangana. The site covers 25.3 acres.
Who is building it?
The applicant is K Srinivas Rao.
Has it been approved?
Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.
Where is it?
In Serilingampalli, Serilingampally, Ranga Reddy, Telangana.
How big is it?
It has a stated cost of ₹2,141 crore and a site of 25.3 acres.
When was it filed?
The application was filed on 2 Jun 2025.
One of 3 filings for this project. The project's main page, with every filing and where each stands: Proposed Residential complex project - Kurra Srinivas Rao
Project details
| Status | Returned to applicant |
|---|---|
| Status since | 19 Jun 2025 |
| Application filed | 2 Jun 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | K Srinivas Rao |
| Land area | 25.3 acres (10.2 ha) |
| Project cost | ₹2,141 crore |
| Village / locality | Serilingampalli |
| Taluk / tehsil | Serilingampally |
| District | Ranga Reddy |
| State | Telangana |
| Location from | Site boundary on record |
| Our reference | WID-TG-02585 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 19 Jun 2025 | Environmental approval granted | 25.3 acres | ₹2,141 crore |
| New project filed 2 Jun 2025 (this page) | Returned to applicant | 25.3 acres | ₹2,141 crore |
| Early planning filed 4 May 2025 | Cleared for impact study | 25.3 acres | ₹2,141 crore |
What the filings say
What is planned
Kurra Srinivas Rao proposes to construct a residential complex in Nanakramguda, Serilingampally. The applicant's project report states that the development will consist of 12 residential towers, two clubhouses, and a temple. The project is designed to accommodate 2,362 residential units.
Each of the 12 residential towers will have a configuration of five basements, a ground floor, and 50 upper floors. The heights of the buildings are specified as 169.8 metres for towers T1 to T11, and 187.5 metres for tower T12. The two clubhouses are planned as follows:
- Club House 1: Five basements, ground floor, three upper floors, and a terrace.
- Club House 2: Five basements, ground floor, four upper floors, and a terrace.
- Temple: Five basements and a ground floor.
The total built-up area is planned at 11,27,671.33 square metres. To support construction, the applicant proposes to install a captive ready-mix concrete batching plant with a capacity of 120 cubic metres per hour.
Layout and design
The project is situated on a total land area of 1,02,213.83 square metres (25.25 acres), with a net land area of 90,433.50 square metres (22.34 acres) after accounting for road widening. The ground coverage is planned at 15,308.41 square metres, representing 16.93% of the net site area. Internal roads and other open spaces will occupy 66,028.13 square metres (73.01%).
Parking facilities are designed to occupy 3,35,818.71 square metres across five basement levels. This area is intended to accommodate 7,079 four-wheelers and 2,700 two-wheelers.
| Item | Detail |
|---|---|
| Total Built-up Area | 11,27,671.33 Sq.m |
| Residential Units | 2,362 |
| Tallest Building Height | 187.5 metres |
| Total Towers | 12 (G+50 floors) |
| Parking Capacity | 7,079 cars, 2,700 two-wheelers |
| Sewage Treatment Plant | 2,300 KLD |
| Greenbelt Area | 9,096.96 Sq.m (10.06%) |
Land and surroundings
The project site is located at Survey Nos. 92 (Part), 93, 94 (part), 95/A, 95 AA (part), 96 (part), and 97 AA (part) in Nanakramguda village. The land use is categorized as partly residential and partly commercial-cum-housing zone. The site is situated on the Deccan plateau, characterized by stable rock masses of granites and gneisses. The applicant's Environmental Impact Assessment (EIA) report notes that the site is currently devoid of rare or endangered species. Nearby ecological features include the KVR Botanical Garden (4.1 km) and Mrugavani National Park (5.5 km).
Water, power and access
The total water demand during the operational phase is estimated at 2,200 kilolitres per day (KLD). This includes 1,457 KLD of fresh water, to be sourced from municipal supply or ground water, and 743 KLD of recycled water. During construction, the demand is estimated at 50 KLD.
Power requirements are projected at 8,000 kVA (maximum peak demand), to be supplied by the Telangana State Southern Power Distribution Company Limited (TSSPDCL). For backup, the applicant plans to install 10 diesel generator sets of 1,250 kVA each. Solar energy utilization is planned for 320 kVA, primarily for street lighting. The site is connected via the service road of the Outer Ring Road.
Environmental safeguards
A sewage treatment plant (STP) with a capacity of 2,300 KLD is proposed. Treated wastewater will be reused for flushing and greenbelt development, with excess discharged to municipal drains. The project includes a dual plumbing system to facilitate this reuse.
Solid waste generation during the operational phase is estimated at 8,312 kg per day of municipal solid waste and 190 kg per day of STP sludge. An area of 500 square metres will be allocated for waste segregation and processing, including an organic waste converter to produce manure for landscaping. For storm water management, the applicant proposes 10 rainwater harvesting pits, each with a capacity of 2 KLD.
Timeline
The total construction period for the entire complex is estimated at 36 months from the date of receiving all necessary approvals. The peak workforce required during this phase is expected to be approximately 200 workers.
Residential Complex Project - Kurra Srinivas Rao site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
882 applications in Ranga Reddy since January 2022 are in the same category (Buildings & townships): 667 approved, 107 filed or under review, and 108 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 25.3 acres, this one is larger than 85% of them.
343 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Serilingampalli, Serilingampally, Ranga Reddy, Telangana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Residential complex project - Kurra Srinivas Rao — environmental approval granted, 0 m away
- Proposed Residential complex project - Kurra Srinivas Rao — cleared for impact study, 0 m away
- Amendment of Environmental Clearance Issued for Proposed Construction Project… — returned to applicant, 0 m away
- Enhancement of Built-Up Area and Change of Building Type - Sastec Elite… — initial checks, 250 m away
- SASTEC ELITE VENTURES LLP (Proposed Commercial Office cum Hotel complex) — environmental approval granted, 250 m away
- Hospital Building Construction Project located at Survey Nos.78, 80, 85, 86,… — environmental approval granted, 500 m away
- Amendment for Proposed construction of TDR Floors for commercial Building… — environmental approval granted, 550 m away
- Commercial Building (Retail & Office) "Two West" by M/s. Terminus Nankramguda… — environmental approval granted, 600 m away
More from K Srinivas Rao in Ranga Reddy
- Amendment of Environmental Clearance Issued for Proposed Construction Project… — returned to applicant
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.